ASSESSMENT ID: LFT-__________ DATE: ______________ TIME: ______________
FACILITY NAME: ______________ LOCATION: ______________ AREA: ______________
LIFT TYPE: Routine ☐ Critical ☐ Engineered ☐ Complex ☐ Personnel ☐ Subsea ☐
LIFT DESCRIPTION: ______________
CRANE/EQUIPMENT ID: ______________ CAPACITY: _____________ tons OPERATOR: ______________
LIFT CLASSIFICATION:
| ☐ ROUTINE LIFT - Standard lift within normal operating parameters, not exceeding 80% of crane capacity, no special hazards, no lifts over live equipment or personnel. | |
|---|---|
| ☐ CRITICAL LIFT - Any lift meeting ONE OR MORE of these criteria: ☐ Lift > 80% of crane rated capacity ☐ Lift over live equipment/process areas ☐ Lift over occupied facilities ☐ Multiple crane lift ☐ Lift of personnel (manbasket/manriding) ☐ Lift in high wind or restricted visibility ☐ Unusual or complex rigging arrangement ☐ Lift of hazardous materials ☐ Lift in environmentally sensitive area ☐ First use of new lift procedure/equipment | |
| ☐ ENGINEERED LIFT - Exceeding 100% of crane rated capacity or requiring engineering analysis. Requires engineered lift plan and PE stamp. |
THIS LIFT IS CLASSIFIED AS: ☐ ROUTINE ☐ CRITICAL ☐ ENGINEERED
IF CRITICAL OR ENGINEERED, A WRITTEN LIFT PLAN IS REQUIRED AND ATTACHED.
LIFT PLAN #: ______________ ATTACHED: Yes ☐ No ☐
| HAZARD CATEGORY | HAZARD DESCRIPTION | POTENTIAL CONSEQUENCE | EXISTING CONTROLS | LIKELIHOOD (1-5) | SEVERITY (A-E) | RISK INDEX |
|---|---|---|---|---|---|---|
| Dropped Objects | -Equipment/ rigging failure -Load instability -Slip/tag line issues -Crane malfunction | -Fatality -Serious injury -Equipment damage -Production loss | -Exclusion zone -Barricading -Tag lines -Proper rigging -Load control -Redundant hoists | 4 (Probable) | E (Catastrophic) | 16 (EXTREME) |
| Crane Stability / Failure | -Crane overturn -Outrigger failure -Boom failure -Swing away from level -Ground subsidence | -Crane tip- over -Structural collapse -Fatality -Multiple injuries | -Ground condition assessment -Outrigger pads -Load indicator -Limit switches -Level sensors | 3 (Occasional) | E (Catastrophic) | 12 (HIGH) |
| Rigging Failure | -Slings failure -Shackle failure -Hook failure -Improper rigging angle -Uncertified gear | -Dropped load -Load runaway -Personnel injury -Equipment damage | -Pre-use inspection -Certified rigging -SWL marked -Angle limits -Redundant slings | 4 (Probable) | D (Hazardous) | 12 (HIGH) |
| Personnel Injury | -Struck by load -Crushed between objects -Swing radius contact -Tag line entanglement -Slips/trips | -Fatality -Crushing -Amputation -Serious injury | -Exclusion zone -Barricades -Tag lines -Hand signals -Banksman -Operator visibility -Lighting | 5 (Almost Certain) | E (Catastrophic) | 20 (EXTREME) |
| Environmental Factors | -High wind (> limits) -Poor visibility -Lightning -Rain/ice -Extreme temps -Sea state (offshore) | -Loss of load control -Crane instability -Collision -Dropped load | -Wind monitoring -Weather limits -Lightning detector -Postpone if needed -DP | 4 (Probable) | D (Hazardous) | 12 (HIGH) |
| Power Lines / Electrical | -Crane contact with power lines -Ground fault -Static discharge | -Electrocution -Fatality -Arc flash -Fire -Equipment damage | -Spotting -Minimum clearance -Barricades -Insulated links -Groundman -Power isolation | 3 (Occasional) | E (Catastrophic) | 12 (HIGH) |
| Multiple Crane Lifts | -Crane-to- crane conflict -Load instability -Uneven load sharing -Comm failure | -Collision -Uneven load sharing -Dropped load -Crane overload | -Lift plan -One supervisor -Comms -Synchron- ization -Load cells -Tilt indicators | 3 (Occasional) | D (Hazardous) | 9 (HIGH) |
LOAD DETAILS:
| LOAD DESCRIPTION: ______________ LOAD WEIGHT: _____________ lbs/kg/tons DIMENSIONS: L: ______ W: ______ H: ______ ft/m LOAD CENTER OF GRAVITY: Marked ☐ Calculated ☐ Estimated ☐ Location: ______________ LIFT POINTS: Number: ______ Type: Padeyes ☐ Lugs ☐ Slings ☐ Chokers ☐ SPECIAL HANDLING: Fragile ☐ Hazardous ☐ Hot ☐ Precision ☐ Other: ______________ |
|---|
CRANE / LIFTING EQUIPMENT:
| CRANE ID: ______________ TYPE: Mobile ☐ Crawler ☐ Pedestal ☐ Overhead ☐ Other: ______________ CONFIGURATION: Boom length: ______ ft Jib: Yes ☐ No ☐ Type: ______________ Fly: ______ ft CAPACITY AT CONFIGURATION: _____________ tons at radius: ______ ft (per load chart) | |
|---|---|
| LIFT CALCULATIONS: LIFT RADIUS: _____________ ft CAPACITY @ RADIUS: _____________ tons LOAD WEIGHT: _____________ tons RIGGING WEIGHT: _____________ tons BLOCK/HOOK WEIGHT: _____________ tons TOTAL LOAD: _____________ tons CAPACITY UTILIZATION: _____________ % (Total Load / Capacity) | |
| MARGIN OF SAFETY: _____________ tons (Capacity - Total Load) | |
| ☐ LIFT WITHIN CAPACITY - Proceed ☐ EXCEEDS CAPACITY (>100%) - REDESIGN REQUIRED ☐ CRITICAL LIFT (>80% or other criteria) - LIFT PLAN REQUIRED |
RIGGING ARRANGEMENT:
| RIGGING METHOD: Single leg ☐ Bridle (2-leg) ☐ 3-leg ☐ 4-leg ☐ Basket ☐ Choker ☐ Other: _________ | |
|---|---|
| SLING CALCULATIONS: SLING TYPE: Wire rope ☐ Synthetic ☐ Chain ☐ Size: ______ in Grade: ______ SLING ANGLE: ______ degrees from vertical ANGLE FACTOR: ______ MAX SLING LOAD: (Load / # legs) x Angle Factor = _____________ tons SLING SWL (Safe Working Load): _____________ tons SLING UTILIZATION: _____________ % (Max Sling Load / SWL) | |
| SHACKLE/HARDWARE: SHACKLE SIZE: ______ tons TYPE: Screw pin ☐ Safety bolt ☐ Other: ______ SHACKLE SWL: _____________ tons LOAD ON SHACKLE: _____________ tons OK: Yes ☐ No ☐ | |
| LIFT POINT SWL: _____________ tons LOAD ON LIFT POINT: _____________ tons OK: Yes ☐ No ☐ |
CRANE INSPECTION (To be completed by Crane Operator):
| ☐ Daily inspection complete - No defects noted ☐ Load chart available and current ☐ Load indicator/limiter functioning - Tested: Yes ☐ No ☐ ☐ Anti-two block functioning - Tested: Yes ☐ No ☐ ☐ Boom angle indicator working ☐ Swing brake working ☐ Hoist brakes working ☐ Wire rope condition good - No kinks, birdcaging, broken wires ☐ Hooks - Safety latches working, no deformation ☐ Hydraulic systems - No leaks ☐ Tires/tracks condition good ☐ Outriggers - Fully extended, pads in place, level ☐ Operator seat/controls functioning ☐ Fire extinguisher in cab - Inspected: ______________ ☐ Crane level - Level within 1% (0.5°): Bubble level OK ☐ Digital OK ☐ |
|---|
RIGGING INSPECTION (To be completed by Rigger/Banksman):
| SLINGS: ☐ All slings have current certification tags ☐ Wire rope slings - No broken wires, kinks, crushing, corrosion ☐ Synthetic slings - No cuts, abrasion, heat damage, UV damage ☐ Chain slings - No stretch, cracks, wear ☐ Slings correct size and type for lift | |
|---|---|
| HARDWARE: ☐ Shackles - Correct size, pins straight, no deformation ☐ Hooks - Safety latches working, no deformation, no cracks ☐ Eye bolts - Shouldered, full engagement, no bending ☐ Lifting beams/spreaders - Certified, no damage ☐ Swivels - Moving freely, no damage ☐ Lifting lugs/padeyes - No deformation, corrosion, cracks | |
| LIFT AREA: ☐ Exclusion zone established - Radius: ______ ft ☐ Barricades in place - Type: ______________ ☐ Warning signs posted ☐ Ground conditions stable - Bearing capacity: ______ tons/sq ft ☐ Overhead obstructions identified - Power lines ☐ Structures ☐ Other: ______ ☐ Underground utilities identified - Locate marks: Yes ☐ No ☐ ☐ Lighting adequate (if night work) ☐ Communications check - Radio channel: ______ Working: Yes ☐ No ☐ |
WEATHER CHECK:
| Current wind speed: ______________ mph/kts Gusts: ______________ mph/kts Wind limit for this lift: ______________ mph/kts (per crane manufacturer) ☐ Wind within limits - Proceed ☐ Wind approaching limits - Monitor closely ☐ Wind EXCEEDS limits - DO NOT PROCEED | |
|---|---|
| Visibility: Good ☐ Fair ☐ Poor ☐ (If poor, postpone lift) Lightning within 10 miles? Yes ☐ No ☐ (If yes, postpone lift) Rain/Ice? Yes ☐ No ☐ (If yes, assess and possibly postpone) |
LIFT PLAN NUMBER: ______________ REVISION: ______ DATE: ______________
PREPARED BY: ______________ TITLE: ______________
REVIEWED BY: ______________ TITLE: ______________
APPROVED BY: ______________ TITLE: ______________
LIFT DESCRIPTION: ______________
______________
ENGINEERING CALCULATIONS:
☐ Load weight verification - Method: ______________ Verified by: ______________
☐ Load distribution analysis - Attached: Yes ☐ No ☐
☐ Crane capacity verification - Multiple configurations checked: Yes ☐ No ☐
☐ Rigging design - Engineered rigging drawing attached: Yes ☐ No ☐
☐ Lift point adequacy - Verified by: ______________
☐ Ground bearing pressure calculation - ______ tons/sq ft OK: Yes ☐ No ☐
☐ Structural analysis of supporting structure - Attached: Yes ☐ No ☐
☐ Wind/weather contingency plan - Attached: Yes ☐ No ☐
LIFT SEQUENCE:
1. ______________
2. ______________
3. ______________
4. ______________
5. ______________
COMMUNICATIONS PLAN:
Primary communication method: Radio channel: ______ Backup method: Hand signals ☐ Other: ______
Communication hierarchy: 1. Lift Supervisor 2. Crane Operator 3. Banksman 4. Other
EMERGENCY PROCEDURES:
☐ Emergency stop signal established - Signal: ______________
☐ Contingency for load hang-up
☐ Contingency for equipment failure
☐ Contingency for weather deterioration
☐ Rescue plan for personnel basket (if applicable)
ATTACHMENTS:
☐ Crane load chart
☐ Site/lift area drawing
☐ Rigging arrangement drawing
☐ Lift sequence diagram
☐ Engineering calculations
☐ Risk assessment
☐ Crane certification
☐ Rigging certification
☐ Personnel competency records
☐ Other: ______________
PERSONNEL BASKET OPERATIONS REQUIRE SPECIAL APPROVAL AND CONTROLS:
BASKET INFORMATION:
☐ Basket certified for personnel lifting - Cert #: ______________ Expiry: ______________
☐ Basket inspected before use - By: ______________ Date: ______________
☐ Basket capacity: ______ persons Maximum load: ______ lbs/kg
☐ Basket has: Self-closing gate ☐ Non-slip floor ☐ Handholds ☐ Tag lines ☐
PERSONNEL LIFTING REQUIREMENTS:
☐ Crane specifically approved for personnel lifting
☐ Crane equipped with secondary braking system
☐ Crane has anti-two-block device
☐ Crane has load indicator with audible alarm
☐ Crane operator specifically trained for personnel lifts
☐ Dedicated signal person in constant communication
☐ Personnel in basket wear full-body harness attached to basket
☐ No other lifts during personnel basket operation
☐ Wind speed limits strictly enforced (typically <15 mph)
☐ Personnel basket operations during daylight only (unless special approval)
PERSONNEL BASKET PRE-USE BRIEFING:
☐ Emergency procedures reviewed
☐ Boarding/disembarking procedures reviewed
☐ Harness attachment reviewed
☐ Communications checked
☐ Weather within limits verified
ATTENDANTS IN BASKET:
1. Name: ______________ Signature: ______________
2. Name: ______________ Signature: ______________
3. Name: ______________ Signature: ______________
4. Name: ______________ Signature: ______________
LIFT SUPERVISOR (Person in charge of the lift):
Name: ______________ Signature: ______________
Responsibilities:
☐ Ensure lift plan is followed
☐ Conduct pre-lift briefing
☐ Verify all checks complete
☐ Control the lift sequence
☐ Stop lift if unsafe conditions develop
CRANE OPERATOR:
Name: ______________ Signature: ______________ Cert #: ______________
Responsibilities:
☐ Operate crane within limitations
☐ Follow signals from lift supervisor/banksman
☐ Monitor crane performance and load indicators
☐ Stop lift if unsafe conditions develop
RIGGER / BANKSMAN:
Name: ______________ Signature: ______________ Cert #: ______________
Responsibilities:
☐ Inspect rigging before use
☐ Attach/detach loads correctly
☐ Guide load using tag lines
☐ Keep personnel clear of lift area
☐ Give clear signals to operator
SIGNAL PERSON (if different from Banksman):
Name: ______________ Signature: ______________
Responsibilities:
☐ Give all crane movement signals
☐ Ensure only one person gives signals
SAFETY WATCH:
Name: ______________ Signature: ______________
Responsibilities:
☐ Monitor exclusion zone
☐ Watch for changing conditions
☐ Stop work if unsafe conditions develop
DATE: ______________ TIME: ______________ LOCATION: ______________
ATTENDEES: (All lift team members must attend and sign)
| NAME ROLE SIGNATURE ______________ ______________ ______________ ______________ ______________ ______________ ______________ ______________ ______________ ______________ ______________ ______________ ______________ ______________ ______________ ______________ ______________ ______________ ______________ ______________ ______________ |
|---|
BRIEFING TOPICS COVERED:
☐ Lift scope and objective
☐ Load weight and dimensions
☐ Crane configuration and capacity
☐ Lift radius and swing path
☐ Rigging arrangement and inspection status
☐ Exclusion zone and barricading
☐ Communication methods and signals
☐ Roles and responsibilities
☐ Potential hazards and controls
☐ Emergency procedures
☐ Weather limits and monitoring
☐ Stop work authority
QUESTIONS / CONCERNS ADDRESSED:
______________
______________
ALL TEAM MEMBERS UNDERSTAND THEIR ROLES AND THE LIFT PLAN.
Lift Supervisor Signature: ______________ Date: ______________
BEFORE EACH LIFT:
| ☐ Pre-lift briefing completed ☐ Area secured - Barricades in place, personnel clear ☐ Communications check - All radios working, same channel ☐ Weather within limits - Wind: ______ mph Vis: Good ☐ ☐ Final rigging check - All connections secure ☐ Tag lines attached and ready ☐ Load balance confirmed ☐ Lift supervisor ready to direct |
|---|
DURING LIFT:
| ☐ Lift smoothly - No sudden movements ☐ Load kept as low as practical while moving ☐ Tag lines used to control load ☐ Constant communication maintained ☐ Load watched for shifting ☐ Personnel stay clear of load and swing radius ☐ Crane operator monitors load indicator continuously ☐ Lift supervisor monitors entire operation |
|---|
AFTER LIFT:
| ☐ Load landed and secured ☐ Rigging removed and inspected for damage ☐ Crane secured (boom down, parking brake set) ☐ Area returned to normal ☐ Post-lift debrief conducted (if needed) ☐ Lift documented (if critical/engineered) |
|---|
| # | DATE | LIFT DESC | LOAD (tons) | CRANE USED | OPERATOR | NOTES | ||
|---|---|---|---|---|---|---|---|---|
| 1 2 3 4 | __________ __________ __________ __________ | __________ __________ __________ __________ | __________ __________ __________ __________ | ____________ ____________ ____________ ____________ | ____________ ____________ ____________ ____________ | ________ ________ ________ ________ |
| HOIST LOAD Forearm up, index finger pointing up, move in small circles | LOWER LOAD Arm extended down, index finger pointing down, move in small circles | SWING (direction) Arm extended, point in direction of swing, move in small circles | STOP Arm extended, hand open, palm down, move side to side | EMERGENCY STOP Both arms waved rapidly |
|---|
| # | ACTION REQUIRED | RESPONSIBLE | DUE DATE | STATUS | ||
|---|---|---|---|---|---|---|
| 1 2 3 4 5 | Annual crane certification due (Crane #1) Replace damaged synthetic sling (S-023) Update critical lift procedure for new crane Calibrate load indicator on Crane #2 Conduct refresher training for riggers | Maintenance Rigger Lift Super Crane Vendor HSE | 03/15/2025 01/20/2025 02/28/2025 01/30/2025 04/15/2025 | Scheduled ☐ Complete ☐ In Progress ☐ Open ☐ Planned ☐ |
ASSESSMENT TEAM:
Name: ______________ Title: Lift Supervisor Signature: ______________
Name: ______________ Title: Crane Operator Signature: ______________
Name: ______________ Title: Rigger/Banksman Signature: ______________
Name: ______________ Title: Safety Officer Signature: ______________
Name: ______________ Title: Engineer (for critical lifts) Signature: ______________
APPROVALS:
Operations Manager: ______________ Date: ______________ Signature: ______________
HSE Manager: ______________ Date: ______________ Signature: ______________
Lift Supervisor: ______________ Date: ______________ Signature: ______________
REVIEW DATE: ______________ NEXT REVIEW DATE: ______________