Free Lifting Operation Permit (Enhanced) template for oil & gas you can edit online and download as PDF. Covers permit information, lift details, lift plan & documentation.
PERMIT NO: LIFT-______________ PTW REFERENCE: PTW-______________
PROJECT/FACILITY: ______________ CONTRACTOR: ______________
LIFT LOCATION: ______________ AREA/ZONE: ______________
LIFT DESCRIPTION: ______________
______________
PERMIT VALIDITY: FROM: ______________ DATE: ______________ TO: ______________ DATE: ______________
(Lifting permits typically valid for ONE SHIFT only - maximum 12 hours)
LIFT CLASSIFICATION: ☐ Routine Lift (< 10 tons) ☐ Critical Lift (10-40 tons) ☐ Heavy Lift (> 40 tons)
☐ Personnel Lift (Man Basket) ☐ Multi-Crane Lift ☐ Tandem Lift
CRANE/EQUIPMENT DETAILS:
Crane Type: ☐ Mobile Crane ☐ Crawler Crane ☐ Tower Crane ☐ Overhead Crane ☐ Truck Mounted ☐ Forklift
☐ Boom Truck ☐ Gantry Crane ☐ Other: ______________
Crane ID/Unit #: ______________ Manufacturer: ______________
Model: ______________ Year of Manufacture: _____________
Capacity (SWL): ______________ tons @ ______________ m radius
Counterweight: ______________ tons Boom Length: ______________ m
LOAD DETAILS:
Load Description: ______________
Load Weight: ______________ tons (Verified: ☐ Yes ☐ No)
Load Dimensions: Length: _______ m Width: _______ m Height: _______ m
Load Centre of Gravity: ______________ Number of Lifts: _______
Lift Radius Required: _______ m Maximum Lift Height: _______ m
LIFT TEAM:
| ROLE | NAME | CERTIFICATION / ID | ||
|---|---|---|---|---|
| Lift Supervisor (Appointed Person) Crane Operator Rigger Level 1 (In-charge) Rigger Level 2 Rigger Level 3 Signalman / Banksman Safety Observer | ________ ________ ________ ________ ________ ________ ________ | Cert #: ______________ Exp: _______ License #: ____________ Exp: _______ Cert #: ______________ Exp: _______ Cert #: ______________ Exp: _______ Cert #: ______________ Exp: _______ Cert #: ______________ Exp: _______ ________ |
| REQUIRED DOCUMENTS ATTACHED: | YES | NO | N/A | REFERENCE |
|---|---|---|---|---|
| Method Statement Risk Assessment (RAMS) Lift Plan (Detailed) Crane Lift Chart / Load Chart Crane Certificate of Thorough Examination Rigging Gear Certificate & Color Code Current Critical Lift Plan (if applicable) Man Basket Certificate & Test Certificate Ground Bearing Capacity Assessment Engineering Assessment (if required) Third Party Inspection Report | ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ | ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ | ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ | Rev #: _________ Ref #: _________ Plan #: _________ Chart #: _________ Date: _________ Last Insp: _________ Approved: _________ SWL: _________ tons Capacity: _______ kPa Ref #: _________ Date: _________ |
LIFT PLAN PREPARED BY (Appointed Person): ______________ DATE: ______________
LIFT PLAN REVIEWED BY (Project Engineer): ______________ DATE: ______________
| CRANE INSPECTION ITEMS: | STATUS | COMMENTS |
|---|---|---|
| Annual / Thorough Examination Certificate valid Pre-use inspection completed Load Moment Indicator (LMI) / Safe Load Indicator (SLI) Anti-two block device working Boom angle indicator accurate Hook block / overhaul ball - condition Wire rope condition (no birdcaging, broken wires) Sheaves & drums - condition Outriggers / stabilizers - operation Outrigger pads / mats - condition & size Tires / tracks - condition Swing brake / house lock Emergency stop / safety devices Cabin / controls condition Fire extinguisher in cab | Yes ☐ No ☐ Yes ☐ No ☐ Working ☐ Fault Yes ☐ No ☐ Yes ☐ No ☐ Good ☐ Fault ☐ Good ☐ Fault ☐ Good ☐ Fault ☐ Good ☐ Fault ☐ Adequate ☐ Not Good ☐ Fault ☐ Working ☐ Not Working ☐ Not Good ☐ Fault ☐ Present ☐ Not | Expiry: ______________ By: ______________ Calibrated: ☐ Yes ☐ No Tested: ______________ Reading: ______________ Safety latch: ☐ Yes ☐ No Inspected: ______________ ________ ________ Size: _______ x _______ mm Pressure: ______________ ________ Tested: ______________ ________ Inspected: ______________ |
| RIGGING GEAR INSPECTION: | STATUS | COMMENTS |
| Slings - Wire rope (condition, tags readable) Slings - Web / Synthetic (condition, tags) Slings - Chain (condition, tags) Shackles - All sizes (condition, pins) Eye bolts / lifting lugs Spreader beam / lifting beam Lifting clamps / plate clamps Turnbuckles / rigging screws Pad eyes / lifting points on load Container twist locks / corner castings Tag lines (condition, length) | Good ☐ Reject Good ☐ Reject Good ☐ Reject Good ☐ Reject Good ☐ Reject Good ☐ Reject Good ☐ Reject Good ☐ Reject Verified ☐ Not Good ☐ Reject Good ☐ Reject | SWL: _______ tons SWL: _______ tons SWL: _______ tons SWL: _______ tons SWL: _______ tons SWL: _______ tons Cert: ____ SWL: _______ tons ________ ________ ________ Length: _______ m |
INSPECTION CONDUCTED BY: ______________ DATE: ______________ TIME: ______________
(Competent Person / Rigger)
GROUND CONDITIONS:
Ground type: ☐ Concrete ☐ Asphalt ☐ Compacted soil ☐ Gravel ☐ Clay ☐ Unknown
Ground bearing capacity required: ______________ kPa / tons/m²
Ground bearing capacity verified: ______________ kPa / tons/m² (By: ______________)
Ground condition: ☐ Dry ☐ Wet ☐ Frozen ☐ Unstable ☐ Other: ______________
OUTRIGGER SET-UP:
Outrigger fully extended? ☐ Yes ☐ No (If No, refer to load chart for restricted capacity)
Outrigger pad size: ______________ x ______________ mm
Outrigger cribbing/mats used? ☐ Yes ☐ No Type: ☐ Timber ☐ Steel ☐ Composite
Cribbing size: ______________ x ______________ mm Thickness: ______________ mm
Cribbing condition: ☐ Good ☐ Damaged (Comments: ______________)
SITE HAZARDS & OBSTRUCTIONS:
Overhead power lines? ☐ Yes ☐ No If Yes: Voltage: ______________ kV Distance: ______________ m
☐ Minimum safe distance maintained (see table below)
Underground services? ☐ Yes ☐ No If Yes: ☐ Marked ☐ Protected ☐ Service drawings consulted
Nearby structures/obstructions? ☐ Yes ☐ No Description: ______________
Other cranes/equipment in area? ☐ Yes ☐ No SIMOPS coordination required? ☐ Yes ☐ No
Public access/roadway nearby? ☐ Yes ☐ No Traffic management required? ☐ Yes ☐ No
WEATHER CONDITIONS:
Current wind speed: ______________ km/h (Maximum allowed: 32 km/h for normal lifts)
☐ Wind speed acceptable? (Stop if >32 km/h or gusty conditions)
Weather conditions: ☐ Clear ☐ Rain ☐ Fog/Mist ☐ Dust storm ☐ Lightning risk
Temperature: _______ °C Visibility: ☐ Good ☐ Poor (stop if poor visibility)
SITE INSPECTED BY (Lift Supervisor): ______________ DATE: ______________
| Voltage (kV) | Minimum Safe Distance (meters) |
|---|---|
| Up to 0.75 kV (750V) 0.75 kV to 75 kV 75 kV to 250 kV 250 kV to 550 kV Above 550 kV | 1.0 m 3.0 m 4.5 m 6.0 m 8.0 m (or as specified by authority) |
NOTE: For cranes with boom length > 30m, increase distances by 50%
Maintain distances even when booms are lowered/raised
Check all hazards applicable to this lifting operation:
CRITICAL HAZARDS: | EQUIPMENT-RELATED HAZARDS:
☐ Toppling / Tip-over / Overturn | ☐ Mechanical failure (crane)
☐ Dropped / Suspended load | ☐ Rigging failure (sling break)
☐ Load instability / shifting | ☐ Hydraulic failure
☐ Overloading (exceeding SWL) | ☐ Electrical fault
☐ Two-blocking | ☐ Outrigger failure / settlement
☐ Collision with structures/equipment | ☐ Boom failure / collapse
☐ Contact with overhead power lines | ☐ Wire rope failure
☐ Personnel struck by load/equipment | ☐ Hook failure / safety latch issue
☐ Person in swing radius / crush zone | ☐ Tyre/track failure
ENVIRONMENTAL HAZARDS: | SITE HAZARDS:
☐ High wind (>32 km/h) | ☐ Uneven/soft ground
☐ Lightning / electrical storm | ☐ Slopes / inclines
☐ Poor visibility (fog, dust, darkness) | ☐ Excavations / trenches nearby
☐ Extreme heat / cold | ☐ Confined area / restricted access
☐ Rain / ice / snow | ☐ Other equipment operating (SIMOPS)
☐ Dust / sand storms | ☐ Pedestrian traffic
HUMAN FACTORS: | LOAD-SPECIFIC HAZARDS:
☐ Incompetent / untrained personnel | ☐ Unstable / irregular load
☐ Communication failure | ☐ Fragile / delicate load
☐ Fatigue / long hours | ☐ Hazardous materials (chemicals, etc.)
☐ Hand-signal miscommunication | ☐ High center of gravity
☐ Distraction / inattention | ☐ Load with loose parts/components
☐ Unauthorized personnel in area | ☐ Lifting multiple items
OTHER HAZARDS (Specify): ______________
______________
| ITEM | YES | NO | N/A | INITIALS | COMMENTS |
|---|---|---|---|---|---|
| Crane positioned on firm level ground Outriggers fully extended and properly set Outrigger pads/mats of adequate size in place Crane level (spirit level checked) Ground bearing capacity verified Load Chart consulted and appropriate for configuration Calculated load within crane capacity at working radius SWL of all rigging equipment adequate for load Rigging inspection completed - all gear in good condition Rigging configuration correct for lift Load weight verified and documented Load centre of gravity identified Load lifting points/pad eyes verified Tag lines attached (if required) Clearance from obstructions verified Overhead power line safe distance maintained Swing radius barricaded / demarcated Exclusion zone established and signed Communication system tested and working Hand signals agreed and understood by all Weather conditions acceptable for lift Lighting adequate (if night work) Emergency procedures briefed to team All personnel wearing correct PPE Pre-lift meeting / toolbox talk completed | ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ | ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ | ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ | ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ ______ | ________ ________ ________ Level: _______ ________ Chart #: _________ Cap: ____ Actual: ___ ________ ________ ________ Weight: _______ tons ________ ________ Number: _______ ________ Distance: _______ m ________ ________ Channel: _______ ________ Wind: ____ km/h Lux level: ______ ________ ________ ________ |
PRE-LIFT CHECKLIST COMPLETED BY (Lift Supervisor): ______________ DATE: ______________
This section MUST be completed for Critical Lifts, Personnel Lifts, Multi-Crane Lifts
| CRITICAL LIFT PLAN REQUIREMENTS: | YES | NO | N/A | INITIALS | COMMENTS |
|---|---|---|---|---|---|
| Detailed Critical Lift Plan prepared and approved Engineering review completed Third party inspection of crane completed Additional safety factors applied (1.5x for critical lifts) Deflection/stress analysis completed (if required) | ☐ ☐ ☐ ☐ ☐ | ☐ ☐ ☐ ☐ ☐ | ☐ ☐ ☐ ☐ ☐ | ______ ______ ______ ______ ______ | Rev #: _________ By: ___________ Report #: ______ Factor: _______ Ref: ___________ |
| PERSONNEL LIFT (MAN BASKET) REQUIREMENTS: | YES | NO | N/A | INITIALS | COMMENTS |
| Man basket certified and load tested within last 12 months Man basket SWL: _______ persons or _______ kg Crane used for personnel lift certified for personnel lifting Anti-two block device working and bypass disabled Positive means of attachment (safety pin/bolt) on hook Suspended personnel wearing full body harness Personnel attached to independent safety line (if required) Communication system in basket Rescue plan for suspended personnel in place | ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ | ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ | ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ | ______ ______ ______ ______ ______ ______ ______ ______ ______ | Cert #: _________ SWL: _________ Config: ________ Tested: ________ ________ ________ ________ Channel: _______ ________ |
| MULTI-CRANE / TANDEM LIFT REQUIREMENTS: | YES | NO | N/A | INITIALS | COMMENTS |
| Detailed lift plan with load sharing calculations All cranes have compatible capacities and characteristics Single lift director appointed Communication protocol established (radio only, no hand signals) Test lift / trial lift completed | ☐ ☐ ☐ ☐ ☐ | ☐ ☐ ☐ ☐ ☐ | ☐ ☐ ☐ ☐ ☐ | ______ ______ ______ ______ ______ | Ref: ___________ ________ Name: __________ Channel: _______ Time: ___________ |
SECTION COMPLETED BY (Lift Supervisor/Engineer): ______________ DATE: ______________
TEST LIFT / TRIAL LIFT:
Test lift performed with load just off ground? ☐ Yes ☐ No Time: ______________
Brakes tested? ☐ Yes ☐ No All systems functioning? ☐ Yes ☐ No
LIFT COMMENCEMENT:
Lift start time: ______________ Lift completion time: ______________
LIFT OBSERVATIONS:
| TIME | OBSERVATION | INITIALS | ||
|---|---|---|---|---|
| ______ ______ ______ ______ | ________ ________ ________ ________ | _______ _______ _______ _______ |
ANY ISSUES DURING LIFT? ☐ No ☐ Yes (describe below):
______________
______________
LIFT SUPERVISOR SIGNATURE: ______________ DATE: ______________
MANDATORY PPE:
☐ Hard hat (with chin strap if required) ☐ Safety glasses ☐ Steel-toed boots
☐ High visibility vest / clothing ☐ Hearing protection ☐ Gloves (rigging gloves)
☐ FRC (Fire Resistant Clothing) if required ☐ Other: ______________
ADDITIONAL SAFETY EQUIPMENT:
☐ Safety harness / fall arrest (for work at height)
☐ Communication radios (Channel: _____) ☐ Backup radios available
☐ Wind speed monitor / anemometer ☐ First aid kit
☐ Fire extinguisher (at crane and lift area) ☐ Spill kit
☐ Barricades / warning tape ☐ Safety signs / placards
☐ Traffic cones / delineators ☐ Flag person (if traffic)
☐ Lighting (for night work) ☐ Generator (backup)
PPE VERIFIED BY (Safety Representative): ______________ DATE: ______________
TOPICS COVERED:
☐ Lift details & sequence ☐ Roles & responsibilities
☐ Load weight & characteristics ☐ Crane capacity & limitations
☐ Rigging configuration ☐ Communication methods & signals
☐ Hazard identification ☐ Control measures
☐ Exclusion zone / barricades ☐ Emergency procedures
☐ Weather constraints ☐ Stop work authority
ATTENDEES:
| NAME | ROLE | COMPANY | SIGNATURE | ||
|---|---|---|---|---|---|
| ________ ________ ________ ________ ________ ________ ________ | ________ ________ ________ ________ ________ ________ ________ | ________ ________ ________ ________ ________ ________ ________ | ________ ________ ________ ________ ________ ________ ________ |
MEETING CONDUCTED BY: ______________ DATE: ______________ TIME: ______________
PERMIT APPLICANT / LIFT SUPERVISOR (Confirms all preparations complete, team briefed, site ready):
I confirm that this lifting operation has been properly planned, all hazards assessed, all
equipment inspected, and the team briefed. Safe to proceed.
Signature: ______________ Date: ______________ Time: ______________
CRANE OPERATOR (Confirms crane in safe condition, load within capacity):
I confirm that the crane is in safe working condition, the load is within capacity at the
working radius, and I understand the lift plan.
Signature: ______________ Date: ______________ Time: ______________
RIGGER IN-CHARGE (Confirms rigging correct and load secure):
I confirm that all rigging is correctly configured, within SWL, and the load is properly
attached and secure.
Signature: ______________ Date: ______________ Time: ______________
SIGNALMAN / BANKSMAN (Confirms communication system and signals):
I confirm that communication systems are working and hand signals are understood by all.
Signature: ______________ Date: ______________ Time: ______________
SAFETY REPRESENTATIVE (If present):
I have observed preparations and confirm they meet safety requirements.
Signature: ______________ Date: ______________ Time: ______________
AREA AUTHORITY / OPERATIONS (Confirms area clear and ready):
Signature: ______________ Date: ______________ Time: ______________
FINAL APPROVAL - PERMIT ISSUED BY (Project Manager / Site Manager):
Signature: ______________ Date: ______________ Time: ______________
PERMIT VALID FOR LIFT BETWEEN: Start: ______________ Date: ______________ End: ______________ Date: ___________
LIFT COMPLETED / SUSPENDED:
Date: ______________ Time: ______________
☐ Lift completed as planned
☐ Lift suspended (reason): ______________
☐ Lift aborted due to emergency/unsafe condition: ______________
CRANE SECURED:
☐ Boom lowered / secured
☐ Engine off / key removed
☐ Outriggers retracted (if mobile)
☐ Crane parked in designated area
☐ Wind down / storm moorings applied (tower crane)
RIGGING EQUIPMENT:
☐ All rigging removed and stored
☐ Rigging inspected for damage after use
☐ Damaged rigging tagged and removed from service
SITE RESTORATION:
☐ Area cleared of equipment and debris
☐ Barricades / warning signs removed
☐ Exclusion zone demobilized
☐ Ground restored (if disturbed)
☐ Area returned to Operations
LIFT SUPERVISOR DECLARATION:
I confirm that the lifting operation has been completed/suspended, all equipment has been
secured, and the area is left in a safe condition.
Signature: ______________ Date: ______________ Time: ______________
AREA AUTHORITY / OPERATIONS (Site handover acceptance):
Signature: ______________ Date: ______________ Time: ______________
Any incidents, near misses, or unsafe conditions during this lifting operation:
☐ No incidents/near misses
☐ Incident occurred (complete below)
☐ Near miss occurred (complete below)
☐ Unsafe condition observed (complete below)
DESCRIPTION: ______________
______________
______________
CORRECTIVE ACTIONS TAKEN: ______________
______________
REPORTED BY: ______________ Date: ______________ Time: ______________
REPORT NUMBER (if applicable): ______________
THIS PERMIT IS VALID ONLY FOR THE SPECIFIED LIFT(S)