Free Hydrocarbon Release Risk Assessment template for oil & gas you can edit online and download as PDF. Covers facility information, leak detection and monitoring systems, hydrocarbon inventory and isolation capabilities.
ASSESSMENT ID: HCR-__________ DATE: ______________ TIME: ______________
FACILITY NAME: ______________ LOCATION: ______________ UNIT: ______________
FACILITY TYPE: Onshore ☐ Offshore ☐ Pipeline ☐ Terminal ☐ Refinery ☐
OPERATOR: ______________ DATE OF REVIEW: ______________ REVISION NUMBER: ______
| PROCESS UNIT/ SYSTEM | HAZARD DESCRIPTION | POTENTIAL CONSEQUENCE | EXISTING CONTROLS | LIKELIHOOD (1-5) | SEVERITY (A-E) | RISK INDEX |
|---|---|---|---|---|---|---|
| Separator / Vessels | -Overpressure / Overfill -Level control failure -Pressure safety valve failure -Corrosion/ erosion | -Catastrophic vessel rupture -BLEVE -Large hydrocarbon release -Fire/Explosion -Fatalities -Environmental damage | -PSV relief -Level transmitters -High-high level alarms -DCS/SIS interlocks -Inspection schedule | 2 (Remote) | E (Catastrophic) | 8 (HIGH) |
| Piping Systems / Manifolds | -Flange leak -Valve stem leak -Gasket blow- out -Corrosion under insulation -Mechanical damage | -Jet fire -Pool fire -Vapor cloud explosion -Toxic exposure -Evacuation -Production loss | -Joint inspection -Leak detection system -Regular leak patrol -Corrosion monitoring -Thermal imaging | 3 (Occasional) | D (Hazardous) | 9 (HIGH) |
| Pumps / Compressors | -Seal failure -Casing rupture -Lube oil leak -Vibration induced failure -Overheating | -Flammable release -Flash fire -Personnel injury -Equipment damage | -Seal monitoring -Mechanical seals -Containment dikes -Vibration monitoring -Remote ESD | 4 (Probable) | C (Major) | 8 (HIGH) |
| Storage Tanks | -Tank overfill -Floating roof failure -Tank bottom leak -Lightning strike -Seal fire -Corrosion | -Major hydrocarbon release -Tank fire -Soil/ground- water contamination -Vapor cloud | -Dike/ bunding -Level gauging -Overfill prevention system -Lightning protection -Cathodic protection | 2 (Remote) | E (Catastrophic) | 8 (HIGH) |
| Loading / Unloading Operations | -Loading arm failure -Hose rupture -Overpressure -Coupling failure -Truck/train movement during connection | -Vapor cloud explosion -Pool fire -Personnel burn -Product loss | -Grounded bonding -Emergency shutdown system -Breakaway couplings -Excess flow valves -Operator training | 3 (Occasional) | D (Hazardous) | 9 (HIGH) |
| Heat Exchangers | -Tube rupture -Gasket failure -Thermal fatigue -Corrosion -Bolting failure | -Rapid pressure build-up -Cross- contamination -Flammable release -H2S exposure | -Pressure relief -Tube integrity monitoring -Thermal analysis -NDT inspection | 3 (Occasional) | D (Hazardous) | 9 (HIGH) |
GAS DETECTION:
| TYPE ________ Point IR Catalytic Open Path IR Ultrasonic H2S O2 Deficiency | LOCATION ________ ________ ________ ________ ________ ________ ________ | # UNITS _______ _______ _______ _______ _______ _______ _______ | LAST CAL ________ ________ ________ ________ ________ ________ ________ | STATUS ________ Operational ☐ Operational ☐ Operational ☐ Operational ☐ Operational ☐ Operational ☐ | ALARM SETTING ____________ ______ %LEL ______ %LEL ______ %LEL ______ dB ______ ppm ______ % | TESTED ________ ________ ________ ________ ________ ________ ________ |
|---|
FIRE DETECTION:
| TYPE ________ Heat Detectors Smoke Detectors Flame Detectors Fusible Plugs | LOCATION ________ ________ ________ ________ ________ | # UNITS _______ _______ _______ _______ _______ | LAST TEST ________ ________ ________ ________ ________ | STATUS ________ Operational ☐ Operational ☐ Operational ☐ Operational ☐ | RESPONSE TIME _____________ ______ sec ______ sec ______ sec N/A | ACTIVATION ________ ________ ________ ________ ________ |
|---|
ISOLATION POINTS:
| SECTION ________ Inlet Isolation Outlet Isolation Emergency Isolation (ESD) Blowdown Valve PSV Inlet | VALVE TAG _________ __________ __________ __________ __________ __________ | VALVE TYPE ____________ Gate/Ball ☐ Gate/Ball ☐ Gate/Ball ☐ Gate/Ball ☐ Gate/Ball ☐ | ACTUATION _________ Manual ☐ Auto ☐ Manual ☐ Auto ☐ Manual ☐ Auto ☐ Manual ☐ Auto ☐ Manual ☐ Auto ☐ | LOCATION ___________ __________ __________ __________ __________ __________ | ACCESSIBILITY _____________ Good ☐ Poor ☐ Good ☐ Poor ☐ Good ☐ Poor ☐ Good ☐ Poor ☐ Good ☐ Poor ☐ | LAST TESTED ________ ________ ________ ________ ________ ________ |
|---|
HYDROCARBON INVENTORY:
| PROCESS UNIT ________ ________ ________ | FLUID TYPE __________ __________ __________ | MAX INVENTORY ________ ________ ________ | PRESSURE ________ ________ ________ | TEMPERATURE ___________ ___________ ___________ | PHASE ________ ________ ________ | CONTAINMENT TYPE ________ ________ ________ |
|---|
WORST-CASE RELEASE SCENARIO (EPA RMP):
| Scenario Description: ______________ Release Rate: _____________ Duration: _____________ Total Quantity: _____________ Affected Area: _____________ Population at Risk: _____________ Flammable Radius: _____________ Toxic Radius: _____________ Environmental Impact: ______________ |
|---|
ALTERNATIVE RELEASE SCENARIO:
| Scenario Description: ______________ Release Rate: _____________ Duration: _____________ Total Quantity: _____________ Mitigating Factors: ______________ |
|---|
PRIMARY CONTAINMENT:
☐ Pressure Relief Devices (PSV/PRV) - Last Tested: _________
☐ Rupture Discs - Last Tested: _________
☐ High Integrity Pressure Protection Systems (HIPPS) - Last Tested: _________
☐ Automatic Shutdown Systems - Last Tested: _________
SECONDARY CONTAINMENT:
☐ Bunds/Dikes - Condition: Good ☐ Needs Repair ☐ Capacity: ________ gallons
☐ Drainage Systems - Last Inspected: _________ Flow Path Clear: Yes ☐ No ☐
☐ Blowdown Systems - Last Tested: _________ Capacity: ________
☐ Flare/Vent Systems - Last Inspected: _________ Status: Operational ☐ Needs Maint ☐
RELEASE DETECTION:
☐ Gas Detection Coverage - Gap Analysis Completed: Yes ☐ No ☐
☐ Flame Detection Coverage - Gap Analysis Completed: Yes ☐ No ☐
☐ CCTV Monitoring - Coverage: _____________ Recording: Yes ☐ No ☐
☐ Operator Patrol Frequency: _____________ Last Patrol: _____________
TIER 1 - LOSS OF PRIMARY CONTAINMENT (LOPC) with greatest consequence:
☐ Release ≥ 1 metric ton (flammable/toxic)
☐ Fire/Explosion with ≥ $100K damage
☐ Evacuation/Community impact
☐ Fatality/Serious injury
TIER 2 - LOSS OF PRIMARY CONTAINMENT (LOPC) with significant consequence:
☐ Release ≥ 100 kg (flammable/toxic)
☐ Fire/Explosion with < $100K damage
☐ Shelter-in-place/Medical treatment
☐ Environmental impact
TIER 3 - CHALLENGES TO SAFETY SYSTEMS:
☐ PSV activation
☐ High-high alarm activation
☐ Near-miss LOPC
☐ Demand on safety system
TIER 4 - OPERATING DISCIPLINE / MANAGEMENT SYSTEM:
☐ Deviations from procedure
☐ Equipment failures (non-LOPC)
☐ Audit findings
☐ Training deficiencies
| # | ACTION REQUIRED | RESPONSIBLE | DUE DATE | STATUS | ||
|---|---|---|---|---|---|---|
| 1 2 3 4 5 | ________ ________ ________ ________ ________ | _____________ _____________ _____________ _____________ _____________ | _____________ _____________ _____________ _____________ _____________ | Open ☐ In Prog ☐ Complete ☐ Open ☐ In Prog ☐ Complete ☐ Open ☐ In Prog ☐ Complete ☐ Open ☐ In Prog ☐ Complete ☐ Open ☐ In Prog ☐ Complete ☐ |
ASSESSMENT TEAM:
Name: ______________ Title: ______________ Signature: ______________
Name: ______________ Title: ______________ Signature: ______________
Name: ______________ Title: ______________ Signature: ______________
Name: ______________ Title: ______________ Signature: ______________
APPROVALS:
Operations Manager: ______________ Date: ______________ Signature: ______________
HSE Manager: ______________ Date: ______________ Signature: ______________
Process Safety Engineer: ______________ Date: ______________ Signature: ______________
REVIEW DATE: ______________ NEXT REVIEW DATE: ______________