Hot Work Operations Risk Assessment template

Free Hot Work Operations Risk Assessment template for oil & gas you can edit online and download as PDF. Covers hot work information, hot work risk assessment matrix, hot work area inspection checklist.

Hot Work Information

ASSESSMENT ID: HOT-__________ DATE: ______________ TIME: ______________

FACILITY NAME: ______________ LOCATION: ______________ UNIT/AREA: ______________

WORK DESCRIPTION: ______________

WORK TYPE: Welding ☐ Grinding ☐ Cutting ☐ Brazing ☐ Soldering ☐ Hot tapping ☐ Other: ______________

EQUIPMENT TO BE USED: ______________

PERMIT NUMBER: ______________ PTW REFERENCE: ______________

Hot Work Risk Assessment Matrix

HAZARD CATEGORYHAZARD DESCRIPTIONPOTENTIAL CONSEQUENCEEXISTING CONTROLSLIKELIHOOD (1-5)SEVERITY (A-E)RISK INDEX
Fire-Ignition of combustibles in area
-Ignition of hydrocarbons
-Sparks entering openings
-Undetected smoldering
-Personnel burns
-Property damage
-Fatality
-Facility shutdown
-Area inspection
-Fire extinguishers
-Fire watch
-Cover combustibles
-Wet down
-Fire blankets
4 (Probable)E (Catastrophic)16 (EXTREME)
Explosion-Ignition of flammable gas/vapor
-Welding on containers with residue
-Confined space explosion
-Multiple fatalities
-Total loss of facility
-Environmental release
-Gas testing
-Continuous monitoring
-Isolation of flammables
-Purging
-Ventilation
-Hot work permit
3 (Occasional)E (Catastrophic)12 (HIGH)
Health Hazards-Fumes/gases from welding (ozone, NOx, CO)
-Coated materials (galvanized, painted)
-Cadmium/ chromium
-Inert gas (argon)
-Respiratory illness
-Metal fume fever
-Poisoning
-Long-term health effects
-Local exhaust ventilation
-Respirator (type: ______)
-LEV
-Work position
-Air monitoring
4 (Probable)D (Hazardous)12 (HIGH)
Physical Hazards-Burns from hot work (metal, slag)
-UV radiation (arc flash)
-Electrical shock
-Compressed gas cylinders (O2, fuel)
-Hot slag
-Skin burns
-Eye injury
-Arc eye (welding flash)
-Electric shock
-Fire from cylinder rupture
-PPE (leather apron, gloves)
-Welding helmet
-Leathers
-Insulated holder
-Cylinder storage
5 (Almost Certain)C (Major)10 (HIGH)
SIMOPS Hazards-Hot work near production operations
-Hot work near other crews
-Conflicting activities
-Adjacent hot work areas
-Ignition of release
-Fire/ explosion
-Injury to others
-Escalation
-SIMOPS permit
-Gas testing
-Continuous monitoring
-Barricading
-Fire watch
-Shutdown plan
4 (Probable)D (Hazardous)12 (HIGH)

Hot Work Area Inspection Checklist

AREA PREPARATION (To be completed before hot work begins)

☐ Area inspected for fire hazards - By: ______________ Date: ______________
☐ Flammable/combustible materials removed within 35 ft (11 m)
☐ Combustible floors wet down or covered with fire blankets/sand
☐ Wall/floor openings covered or protected to prevent sparks from entering
☐ Fire-resistant covers/blankets in place to protect equipment
☐ All flammable liquid/gas lines in area isolated and blanked
☐ Adjacent areas checked for combustible materials/atmospheres
☐ Sewers, pits, trenches in area covered or sealed
☐ Fire extinguishers in place and accessible - Type: ______________ #: ______
☐ Fire hoses connected and ready - Hose #: ______________ Pressure: ______ psi
☐ Fire alarm pull station accessible - Location: ______________
☐ Emergency exits clear and accessible
☐ "HOT WORK IN PROGRESS" signs posted
☐ Barricades/warning tape in place around work area

GAS TESTING:

TEST TIMELOCATIONO2 %LEL %TOXIC (ppm)TESTERCOMMENTS
___________ ___________ ___________ ___________ ___________Work area 10 ft radius Adjacent area Below work area Pits/trenches_______ _______ _______ _______ _______________ ________ ________ ________ ___________________ ___________ ___________ ___________ ______________________ ___________ ___________ ___________ ___________________ ________ ________ ________ ________

ACCEPTABLE RANGES: O2: 19.5-23.5% LEL: <10% (Hydrocarbon area) / <5% (Special area)

☐ Continuous gas monitoring required - Monitor ID: ______________ Location: ______________

☐ Frequent re-testing required - Frequency: ______________

Hot Work Equipment Inspection

WELDING/CUTTING EQUIPMENT:

EQUIPMENT ________ Welding machine Welding leads/cables Electrode holder Ground clamp Welding helmet/lens Torch (cutting/welding) Flash arrestors Hose condition Hose connections/fittings Cylinder carts Cylinder caps Cylinder storageINSPECTED _________ Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes/NoCONDITION __________ Good/Damage Good/Damage Good/Damage Good/Damage Good/Damage Good/Damage Present Good/Damage Tight Good/Damage| Secured properly Present Upright/securedCOMMENTS ________ ________ ________ ________ ________ Shade #: _____ ________ On both O2 and fuel No leaks/cuts Clamps/ferrules in place In place when not in use O2 & fuel separated ≥20 ft

FIRE EXTINGUISHERS:

TYPE _________ ABC (10#) CO2 Water Hose reelLOCATION ________ At work area At work area Nearby 50 ft from areaLAST INSPECT ____________ ____________ ____________ ____________ ____________PRESSURE ________ Good/Low Good/Low Good/Low Good/LowSTATUS _________ Ready Ready Ready ReadySUITABLE FOR WORK? ________ Yes ☐ No ☐ Yes ☐ No ☐ Yes ☐ No ☐ Yes ☐ No ☐

Hot Work Permit

PERMIT NUMBER: HOT-_____________ DATE: ______________ EXPIRY: ______________

WORKER INFORMATION:

Welder/Operator: ______________ Company: ______________ Cert #: ______________

Fire Watch: ______________ Company: ______________ Trained: Yes ☐ No ☐

Supervisor: ______________ Company: ______________

DURATION:

Start Date: ______________ Start Time: ______________ End Date: ______________ End Time: ______________

(Hot work permits typically valid for one shift only - maximum 12 hours)

SPECIAL CONDITIONS:

______________

______________

FIRE WATCH REQUIREMENTS:

☐ Fire watch required during work

☐ Fire watch required for 30/60 minutes after work (for smoldering fires)

☐ Fire watch location: At work area ☐ Adjacent areas ☐ Below work ☐ Both ☐

☐ Fire watch equipment: Radio ☐ Extinguisher ☐ Hose ☐ Fire blanket ☐

AUTHORIZATIONS:

Area Authority: ______________ Signature: ______________ Time: ______________

PTW Coordinator: ______________ Signature: ______________ Time: ______________

HSE/Safety: ______________ Signature: ______________ Time: ______________

I HAVE READ AND UNDERSTAND THIS PERMIT:

Welder: ______________ Signature: ______________ Time: ______________

Fire Watch: ______________ Signature: ______________ Time: ______________

Fire Watch Duties And Checklist

FIRE WATCH RESPONSIBILITIES:

☐ Maintain continuous watch during hot work

☐ Watch for fires in all exposed areas

☐ Have fire extinguishing equipment ready

☐ Know how to activate fire alarm

☐ Know how to call for help

☐ Watch for changing conditions

☐ Stop work if unsafe conditions develop

☐ Maintain communication with welder

☐ Remain in area until relieved

☐ Perform post-work fire watch (30-60 min)

FIRE WATCH LOG:

TIMECONDITIONSOBSERVATIONSFIRE WATCH INITIALS
___________ ___________ ___________ ___________ ___________ ___________Normal/Alert Normal/Alert Normal/Alert Normal/Alert Normal/Alert Normal/Alert________ ________ ________ ________ ________ ________________ ________ ________ ________ ________ ________

Hot Work On Or Near Process Equipment - Special Precautions

IS WORK ON OR NEAR:

☐ Piping/vessels that HAVE contained flammables?

☐ Piping/vessels that HAVE contained toxics?

☐ Piping/vessels currently in service?

☐ Electrical equipment?

☐ Coated/painted surfaces?

IF YES TO ANY ABOVE, COMPLETE THIS SECTION:

CONTAINER/PIPE PREPARATION:
☐ Isolated (blinded/ disconnected) - Method: ______________ Verified by: ______________
☐ Drained and depressurized - Pressure: 0 psi ☐ Verified by: ______________
☐ Purged - Method: ______________ Duration: ______________ Verified by: ______________
☐ Cleaned - Method: ______________ Verified by: ______________
☐ Ventilated - Method: ______________ Verified by: ______________
☐ Tested for flammables - Result: <10% LEL ☐ Tested by: ______________
☐ Tested for toxics - Result: Acceptable ☐ Tested by: ______________
☐ Grounded/bonded - Method: ______________ Verified by: ______________
SPECIAL TECHNIQUES:
☐ Hot tap procedure required - Procedure #: ______________
☐ Positive pressure maintained - Medium: ______________ Pressure: ______ psi
☐ Inert atmosphere maintained - Gas: ______________ Monitoring: ______________
☐ Continuous gas monitoring required - Monitor ID: ______________
☐ Additional fire protection - Type: ______________ Location: ______________

Personal Protective Equipment (Ppe) For Hot Work

MINIMUM PPE FOR HOT WORK:

☐ Flame Resistant (FR) Clothing - Material: ______________ Condition: Good ☐ Damaged ☐
☐ Welding Leathers - Jacket ☐ Apron ☐ Sleeves ☐ Condition: Good ☐ Damaged ☐
☐ Welding Gloves - Type: ______________ Condition: Good ☐ Damaged ☐
☐ Welding Helmet - Shade #: ______ Auto-darkening ☐ Fixed shade ☐ Condition: Good ☐ Damaged ☐
☐ Safety Glasses (under helmet) - Condition: Good ☐ Damaged ☐
☐ Hearing Protection - Type: ______________ Condition: Good ☐ Damaged ☐
☐ Steel Toe Boots - Condition: Good ☐ Damaged ☐
☐ Respiratory Protection - Type: ______________ Cartridge: ______________
☐ Head Protection - Hard hat ☐ Welding cap ☐
☐ Leather spats/gaiter - Required for overhead work? Yes ☐ No ☐

PPE VERIFICATION:

I confirm that all personnel involved have the required PPE and it is in good condition:

Supervisor: ______________ Signature: ______________ Date: ______________

Post-Hot Work Procedures

WORK COMPLETION:

☐ Work completed at: ______________ Date: ______________
☐ Equipment shut down and secured
☐ Cylinder valves closed and caps on
☐ Work area cleaned of debris/slag
☐ All combustible materials removed
☐ Fire extinguishers returned to normal location
☐ Barricades/signs removed

POST-WORK FIRE WATCH:

FIRE WATCH REQUIRED AFTER WORK COMPLETION:
☐ 30-minute fire watch (for normal hot work)
☐ 60-minute fire watch (for high-risk work, near combustibles)
☐ Extended fire watch required - Duration: ______________ Reason: ______________
POST-WORK FIRE WATCH LOG:
TIMEAREA CHECKEDOBSERVATIONSFIRE WATCH INITIALS
___________ ___________ ___________ ___________ ___________Work area Below work Adjacent Work area All areas________ ________ ________ ________ ________________ ________ ________ ________ ________

FINAL INSPECTION:

I have inspected the work area and confirmed no signs of fire or smoldering. Fire Watch: ______________ Signature: ______________ Time: ______________ Supervisor: ______________ Signature: ______________ Time: ______________

Hot Work Permit Closure

PERMIT CLOSURE CHECKLIST:

☐ Work completed per permit
☐ Post-work fire watch completed
☐ Area inspected and found safe
☐ Equipment removed/stored properly
☐ Gas cylinders removed or secured
☐ Fire extinguishers in place
☐ Barricades removed
☐ Signs removed
☐ Area returned to normal condition
☐ Permit returned to PTW office

CLOSURE SIGNATURES:

Supervisor: ______________ Signature: ______________ Time: ______________

PTW Coordinator: ______________ Signature: ______________ Time: ______________

PERMIT CLOSED AT: ______________ DATE: ______________

Emergency Procedures For Hot Work

IN CASE OF FIRE:

1. STOP WORK IMMEDIATELY

2. Sound the alarm - Pull station location: ______________

3. Attempt to extinguish if small - Use appropriate extinguisher

4. EVACUATE if fire cannot be controlled

5. Account for personnel at muster point: ______________

6. Notify emergency response: ______________ Phone: ______________

IN CASE OF GAS RELEASE / ALARM:

1. STOP WORK IMMEDIATELY

2. Shut off all ignition sources

3. Evacuate area

4. Follow facility emergency procedures

IN CASE OF INJURY:

1. STOP WORK

2. Provide first aid

3. Call for medical assistance: ______________ Phone: ______________

4. Notify supervisor

Action Plan And Corrective Actions

#ACTION REQUIREDRESPONSIBLEDUE DATESTATUS
1 2 3 4Replace worn welding leads (insulation cracked) Calibrate gas monitor #HW-03 Replenish fire blanket at welding station _____________________ _____________ _____________ __________________________ _____________ _____________ _____________Open ☐ In Prog ☐ Complete ☐ Open ☐ In Prog ☐ Complete ☐ Open ☐ In Prog ☐ Complete ☐ Open ☐ In Prog ☐ Complete ☐

Assessment Team And Approval

ASSESSMENT TEAM:

Name: ______________ Title: Welding Supervisor Signature: ______________

Name: ______________ Title: Safety Officer Signature: ______________

Name: ______________ Title: Fire Watch Signature: ______________

Name: ______________ Title: Area Authority Signature: ______________

APPROVALS:

Operations Manager: ______________ Date: ______________ Signature: ______________

HSE Manager: ______________ Date: ______________ Signature: ______________

PTW Coordinator: ______________ Date: ______________ Signature: ______________

REVIEW DATE: ______________ NEXT REVIEW DATE: ______________