Scaffolding Risk Assessment template

Free Scaffolding Risk Assessment template for construction you can edit online and download as PDF. Covers scaffold project information, scaffold design and engineering - osha 29 cfr 1926.451(a), scaffold component inspection.

Scaffold Project Information

ASSESSMENT ID: SCF-__________ DATE: ______________ TIME: ______________

PROJECT: ______________ LOCATION: ______________ CONTRACTOR: ______________

SCAFFOLD TYPE:

☐ Supported ☐ Suspended ☐ Mobile ☐ Frame ☐ System ☐ Tube & Clamp ☐ Pole

☐ Pump Jack ☐ Ladder Jack ☐ Mast Climber ☐ Other: ______________

SCAFFOLD DIMENSIONS:

Height: ______ m/ft Length: ______ m/ft Width: ______ m/ft # of Tiers: ______

Maximum Load Capacity: ______ kg (lbs) Intended Load: ______ kg (lbs)

SCAFFOLD ERECTOR: ______________ COMPETENT PERSON: ______________

ERECTION DATE: ______________ LAST INSPECTION: ______________ NEXT INSPECTION: ______________

Scaffold Design And Engineering - OSHA 29 Cfr 1926.451(A)

DESIGN REQUIREMENTS:

☐ Designed by qualified person: ______________ Date: ___________

☐ Design drawings available: Yes ☐ No ☐ Drawing #: ______________

☐ Load calculations completed: Yes ☐ No ☐ Capacity: ______ psf (kPa)

☐ Wind load considerations: Yes ☐ No ☐ Max wind speed: ______ mph

SCAFFOLD CLASSIFICATION:

☐ Light Duty (25 lbs/ft²) ☐ Medium Duty (50 lbs/ft²) ☐ Heavy Duty (75 lbs/ft²)

☐ Special Duty (designed for specific loads): ______________

ENGINEERING CERTIFICATION:

"I certify that this scaffold design meets all applicable OSHA requirements and is safe for the intended

use when erected according to these specifications."

Name: ______________ PE #: ______________ Date: ___________ Signature: ___________

Scaffold Component Inspection

COMPONENT ________ Frames Cross Braces Base Plates Screw Jacks Guardrails Midrails Toeboards Planks/Decks Couplers/Clamps Access LadderMANUFACTURER ________ ________ ________ ________ ________ ________ ________ ________ ________ ________ ________MODEL ____________ ____________ ____________ ____________ ____________ ____________ ____________ ____________ ____________ ____________ ____________CONDITION ________ Good ☐ Bad ☐ Good ☐ Bad ☐ Good ☐ Bad ☐ Good ☐ Bad ☐ Good ☐ Bad ☐ Good ☐ Bad ☐ Good ☐ Bad ☐ Good ☐ Bad ☐ Good ☐ Bad ☐ Good ☐ Bad ☐RATING ____________ ______ lbs ______ lbs ______ lbs ______ lbs ______ lbs ______ lbs ______ lbs ______ lbs ______ lbs ______ lbsREPLACEMENT DATE ________ ________ ________ ________ ________ ________ ________ ________ ________ ________ ________

INSPECTION FINDINGS:

______________

______________

INSPECTED BY: ______________ DATE: ___________

Scaffold Foundation And Support - OSHA 29 Cfr 1926.451(B)

FOUNDATION TYPE:

☐ Concrete slab ☐ Compacted gravel ☐ Asphalt ☐ Soil ☐ Mud sills ☐ Other: ______________

FOUNDATION ASSESSMENT:

Bearing capacity: ______ psf (kPa) Required capacity: ______ psf (kPa) Adequate? Yes ☐ No ☐

Level? Yes ☐ No ☐ Slope: ______ % Drainage adequate? Yes ☐ No ☐

Frost heave potential? Yes ☐ No ☐ Settlement observed? Yes ☐ No ☐

BASE PLATES AND MUD SILLS:

☐ Base plates installed on all legs ☐ Mud sills used (size: ______ x ______)

☐ Screw jacks adjusted for leveling ☐ Maximum screw jack extension: ______ inches (≤ 12" required)

☐ Base plates secured to prevent movement

ADJACENT CONDITIONS:

☐ Excavations nearby? Yes ☐ No ☐ Distance: ______ ft Protected? Yes ☐ No ☐

☐ Vehicle traffic nearby? Yes ☐ No ☐ Barriers in place? Yes ☐ No ☐

☐ Overhead hazards? Yes ☐ No ☐ Description: ______________

☐ Underground utilities? Yes ☐ No ☐ Locates completed? Yes ☐ No ☐

Scaffold Erection And Dismantling Hazards

ERECTION/DISMANTLING PLAN:

Plan reference: ______________ Prepared by: ______________ Date: ___________

Sequence documented? Yes ☐ No ☐ Critical lifts identified? Yes ☐ No ☐

FALL PROTECTION DURING ERECTION:

☐ Personal fall arrest system required ☐ Lanyards with shock absorbers

☐ Anchor points identified: ______________

☐ Tie-off required at all times above ______ ft

☐ Fall protection plan for erectors: ______________

MATERIAL HANDLING:

☐ Crane/hoist used for material handling ☐ Manual hoisting ☐ Gin wheels

☐ Material hoist inspected? Yes ☐ No ☐ Date: ___________

☐ Hoist operator qualified? Yes ☐ No ☐ Name: ______________

☐ Tag lines used for swinging loads? Yes ☐ No ☐

☐ Material stacking limited to rated capacity

ERECTION TEAM:

Lead erector: ______________ Experience: ______ years Certified? Yes ☐ No ☐

Team members: ______________ ______________ ______________

Communication method: ☐ Hand signals ☐ Radio ☐ Verbal ☐ Other: ______________

Scaffolding Hazard Identification And Risk Assessment

HAZARDCAUSEPOTENTIAL CONSEQUENCEEXISTING CONTROLSLIKELIHOOD (1-5)SEVERITY (1-5)RISK RATING (L x S)
Scaffold Collapse-Improper assembly
-Overloading
-Inadequate foundations
-Missing components
-Damaged parts
-Inadequate ties
-Multiple fatalities
-Crush injuries
-Equipment damage
-Adjacent property damage
-Engineered design
-Competent person inspection
-Load capacity signs
-Tie-ins
-Foundation preparation
2 (Remote)5 (Catastrophic)10 (HIGH)
Falls from Height-Missing guardrails
-Unprotected edges
-Unsafe access (ladders)
-Slippery surfaces
-Climbing cross braces
-Ice/snow
-Fatalities
-Paralysis
-Broken bones
-Head injury
-Permanent disability
-Guardrails (top, mid, toeboard)
-Personal fall arrest
-Safe access (ladders, stairs)
-Non-slip surfaces
-Training
4 (Probable)5 (Catastrophic)20 (EXTREME)
Falling Objects/ Tools-No toeboards
-Unsecured materials
-Overhead work
-Wind
-Poor housekeeping
-Struck-by injuries
-Head injury
-Fatality
-Property damage
-Public injury
-Toeboards (4" min)
-Debris nets
-Tool tethers
-Canopies
-Barricades
-Exclusion zones
-Material storage limits
4 (Probable)4 (Critical)16 (EXTREME)
Overloading-Exceeding rated load
-Material stockpiling
-Concentrated loads
-Dynamic loads (equipment)
-Multiple workers
-Deck failure
-Structural damage
-Collapse
-Injury
-Load capacity signs posted
-Material management plan
-Regular inspection
-Training
3 (Occasional)4 (Critical)12 (HIGH)
Electrical Hazards-Contact with power lines
-Energized equipment
-Improper grounding
-Damaged cords
-Wet conditions
-Electrocution
-Burns
-Cardiac arrest
-Fall from shock
-Maintain safe distance (10' for <50kV, more for higher)
-Insulated tools
-Power line de- energized or moved
2 (Remote)5 (Catastrophic)10 (HIGH)
Instability (Overturning)-Inadequate ties/guys
-Wind loading
-Eccentric loads
-Mobile scaffold movement
-Unlocked casters
-Uneven ground
-Scaffold tipping
-Fall of scaffold
-Injury to workers
-Property damage
-Tie-ins at required intervals
-Height/ width ratio limits
-Outriggers
-Brakes locked
-Wind monitoring
3 (Occasional)4 (Critical)12 (HIGH)
Plank/Deck Failure-Damaged planks
-Improper span
-Overloading
-Not secured
-Missing planks
-Split wood planks
-Fall through
-Injury
-Collapse
-Fatality
-Grade stamped planks
-Proper overlap (12" min)
-Secured to prevent movement
-Regular inspection
-Load limits
3 (Occasional)4 (Critical)12 (HIGH)
Access Hazards-Missing ladder
-Improper ladder placement
-Climbing braces
-Icy/slippery rungs
-No handhold access
-Fall while accessing scaffold
-Trips
-Musculoskeletal injuries
-Safe ladder access (extend 3' above platform)
-Stairway towers
-Gates on ladder openings
4 (Probable)4 (Critical)16 (EXTREME)
Adverse Weather-Wind
-Rain
-Ice/Snow
-Extreme heat
-Lightning
-High winds
-Loss of balance
-Slips/falls
-Reduced visibility
-Hypothermia
-Heat stress
-Lightning strike
-Weather monitoring
-Work suspension criteria
-Non-slip surfaces
-Tie-offs in high winds
3 (Occasional)3 (Major)9 (MEDIUM)

Suspended Scaffolds (If Applicable) - OSHA 29 Cfr 1926.451(G)

SUSPENDED SCAFFOLD TYPE:

☐ Two-point (swing stage) ☐ Multi-point ☐ Boatswain's chair ☐ Catenary ☐ Float

SUSPENSION EQUIPMENT:

Hoist type: ☐ Electric ☐ Manual ☐ Air

Rated capacity: ______ lbs Serial #: ______________ Last test date: ___________

Wire rope: Diameter: ______ Condition: Good ☐ Fair ☐ Poor ☐ Replacement date: ___________

OUTRIGGER BEAMS/CORNER BEAMS:

☐ Secured against movement ☐ Counterweights installed ☐ Tied back to structure

☐ Vertical pickup points used ☐ Stop bolts installed

FALL PROTECTION FOR SUSPENDED SCAFFOLDS:

☐ Independent lifeline required ☐ Personal fall arrest system ☐ Tied off to structure

☐ Lanyard length limited to prevent hitting lower level

STABILITY REQUIREMENTS:

☐ Scaffold level ☐ Guardrails in place ☐ Toeboards installed

☐ Platform secured to hangers ☐ Maximum platform deflection: ______ inches

Mobile Scaffolds (If Applicable) - OSHA 29 Cfr 1926.452(W)

MOBILE SCAFFOLD TYPE:

☐ Rolling tower ☐ Manual propelled ☐ Powered ☐ Work platform

DIMENSIONS:

Height: ______ ft Base width: ______ ft Base length: ______ ft

Height to base width ratio: ______ (max 4:1 when stationary, 3:1 when moving)

CASTERS AND WHEELS:

☐ Locking casters with positive locks ☐ Swivel locks engaged when stationary

☐ Casters rated for load ☐ Condition: Good ☐ Fair ☐ Poor ☐

MOVING PROCEDURES:

☐ Workers removed before moving ☐ Materials secured ☐ Pushed at base only

☐ Surface clear of debris/holes ☐ Level surface only ☐ Obstructions removed

STABILIZATION:

☐ Outriggers installed (if required) ☐ Screw jacks adjusted to level

☐ Ties or guys required at height? Yes ☐ No ☐

Fall Protection Systems - OSHA 29 Cfr 1926.451(G)(1)

GUARDRAIL SYSTEMS:

☐ Top rail: Height 42-45 inches Condition: ______________ Installed on all open sides

☐ Mid rail: Height ~21 inches Condition: ______________ Installed on all open sides

☐ Toeboard: 4 inches minimum Condition: ______________ Installed on all open sides

☐ Posts: Spacing ≤ 8 feet Condition: ______________

☐ Guardrails capable of withstanding 200 lbs force

PERSONAL FALL ARREST SYSTEMS (PFAS):

☐ PFAS required when guardrails not feasible ☐ Full body harness

☐ Lanyard with shock absorber ☐ Self-retracting lifeline (SRL)

☐ Anchor points: ______________ Rated capacity: 5,000 lbs

☐ Clearance calculation: Free fall ≤ 6 ft, Total fall distance: ______ ft

☐ Rescue plan in place: ______________

SAFETY NETS:

☐ Nets installed when guardrails/PFAS not feasible ☐ Drop test completed

☐ Nets extend 8-13 feet from edge ☐ No debris in nets

Scaffold Inspection Checklist - OSHA 29 Cfr 1926.451(F)(3)

INSPECTOR: ______________ DATE: ______________ TIME: ______________

COMPETENT PERSON DESIGNATION: Yes ☐ No ☐ TRAINING CURRENT: Yes ☐ No ☐

INSPECTION ITEMSATISFACTORYDEFECT FOUNDCORRECTIVE ACTION
PRE-USE INSPECTION:
1. Scaffold level and plumb
2. Base plates/sills in place and undamaged
3. Screw jacks extended properly (≤ 12")
4. Frames vertical and properly connected
5. Cross braces installed and secured
☐ Yes
☐ Yes
☐ Yes
☐ Yes
☐ Yes
☐
☐
☐ N/A
☐
☐
________ ________ ________ ________ ________
GUARDRAILS AND FALL PROTECTION:
6. Top rails in place (42-45")
7. Mid rails in place (~21")
8. Toeboards installed (4")
9. Access ladder/stairs safe and secure
10. No missing planks or open holes
☐ Yes
☐ Yes
☐ Yes
☐ Yes
☐ Yes
☐
☐
☐
☐
☐
________ ________ ________ ________ ________
PLANKING/DECKS:
11. Planks in good condition (no splits, cracks)
12. Planks properly overlapped (12" min)
13. Planks secured to prevent movement
14. Full decking provided on work levels
15. No cantilevered planks unless designed
☐ Yes
☐ Yes
☐ Yes
☐ Yes
☐ Yes
☐
☐ N/A
☐
☐
☐
________ ________ ________ ________ ________
TIES AND BRACING:
16. Ties installed at required intervals (max 26')
17. Ties secured to structure
18. Guys/bracing adequate for height
☐ Yes
☐ Yes
☐ Yes
☐
☐
☐ N/A
________ ________ ________
LOADS AND CAPACITY:
19. Load capacity signs posted
20. Materials stored within capacity limits
21. No excessive concentrated loads
☐ Yes
☐ Yes
☐ Yes
☐
☐
☐
________ ________ ________
ELECTRICAL SAFETY:
22. Safe distance from power lines (>10')
23. Electrical cords in good condition
24. Tools properly grounded/GFCI protected
☐ Yes
☐ Yes
☐ Yes
☐
☐
☐
________ ________ ________
HOUSEKEEPING:
25. Platforms clear of debris/tripping hazards
26. Materials stored neatly
27. Access clear and unobstructed
☐ Yes
☐ Yes
☐ Yes
☐
☐
☐
________ ________ ________

OVERALL ASSESSMENT:

Is scaffold safe for use? Yes ☐ No ☐ (If No, tag out and remove from service)

CORRECTIVE ACTIONS TAKEN:

______________

______________

INSPECTOR SIGNATURE: ______________ DATE: ___________

Daily Scaffold Inspection Log

DATE ___________ ___________ ___________ ___________ ___________INSPECTOR ________ ________ ________ ________ ________SHIFT Day ☐ Night ☐ Day ☐ Night ☐ Day ☐ Night ☐ Day ☐ Night ☐ Day ☐ Night ☐CONDITIONS ____________ ____________ ____________ ____________ ____________DEFECTS FOUND _____________ _____________ _____________ _____________ _____________CORRECTIVE ACTION ________ ________ ________ ________ ________SIGNATURE ________ ________ ________ ________ ________

Scaffold Tag System

CURRENT SCAFFOLD STATUS:

☐ GREEN TAG - SAFE FOR USE

Date: ___________ Inspector: ______________

Capacity: ______ psf Last inspection: ___________

☐ YELLOW TAG - CAUTION - RESTRICTED USE

Restriction: ______________

Date: ___________ Inspector: ______________

☐ RED TAG - UNSAFE - DO NOT USE

Reason: ______________

Date: ___________ Inspector: ______________

TAG LOCATION: ______________ TAG #: ______________

Scaffold Erection And Dismantling Permit

PERMIT TYPE: ☐ Erection ☐ Dismantling ☐ Modification ☐ Relocation

PERMIT #: SCF-P-__________ DATE: ______________ TIME: ______________

SCAFFOLD ID/LOCATION: ______________

WORK DESCRIPTION: ______________

REQUIREMENTS VERIFIED:

☐ Competent person on site: ______________

☐ Erection plan reviewed

☐ Fall protection available and inspected

☐ Tools and equipment inspected

☐ Materials inspected

☐ Weather conditions suitable (wind < 25 mph)

☐ Area below barricaded

☐ Overhead hazards identified

☐ Electrical hazards identified

☐ Communication system established

☐ Emergency response plan reviewed

☐ First aid kit available

☐ Fire extinguisher available

AUTHORIZED WORKERS:

1. ______________ 2. ______________ 3. ______________

4. ______________ 5. ______________ 6. ______________

I CONFIRM THAT ALL SAFETY REQUIREMENTS HAVE BEEN MET AND WORK CAN PROCEED SAFELY.

SUPERVISOR: ______________ SIGNATURE: ______________ DATE: ___________

COMPETENT PERSON: ______________ SIGNATURE: ______________ DATE: ___________

PERMIT VALID: FROM: ___________ TO: ___________ EXTENDED: Yes ☐ No ☐ NEW EXPIRY: ___________

Scaffold Training And Competency Verification - OSHA 29 Cfr 1926.454

TRAINING REQUIREMENTS:

All employees working on scaffolds must be trained by a qualified person to recognize hazards and

understand procedures to control or minimize those hazards.

EMPLOYEE NAME ________ ________ ________ ________JOB ROLE ________ ________ ________ ________TRAINING TOPICS ________ ________ ________ ________DATE ___________ ___________ ___________ ___________TRAINER ________ ________ ________ ________

COMPETENT PERSON DESIGNATION:

Name: ______________ Title: ______________ Experience: ______ years

Training completed:

☐ OSHA scaffold competent person training Date: ___________ Provider: ______________

☐ Specific scaffold type training Date: ___________ Type: ______________

☐ Fall protection training Date: ___________

☐ Hazard identification training Date: ___________

☐ Emergency procedures training Date: ___________

COMPETENT PERSON DUTIES:

☐ Daily scaffold inspections

☐ Oversee erection/dismantling

☐ Train employees on scaffold safety

☐ Identify and correct hazards

☐ Stop work when unsafe conditions exist

Scaffold Emergency Response Plan

POTENTIAL EMERGENCIES:

☐ Scaffold collapse ☐ Fall from height ☐ Electrical contact ☐ Medical emergency

☐ Severe weather ☐ Fire ☐ Tool/material strike ☐ Rescue situation

EMERGENCY CONTACTS:

EMERGENCY: 911

Site Safety Officer: ______________ Phone: ______________

Competent Person: ______________ Phone: ______________

Project Manager: ______________ Phone: ______________

Nearest Hospital: ______________ Phone: ______________

RESCUE PROCEDURES FOR FALL ARREST:

1. Assess situation - DO NOT become victim

2. Call 911 - advise of suspended worker

3. Attempt to communicate with suspended worker

4. Initiate pre-planned rescue:

☐ Self-rescue (if possible)

☐ Aerial lift rescue

☐ Ladder rescue

☐ Mechanical hoist rescue

☐ Wait for emergency services

5. Provide first aid after rescue

6. Complete incident report

RESCUE EQUIPMENT LOCATION: ______________

SCAFFOLD EVACUATION PROCEDURES:

1. Stop work immediately

2. Descend using safe access

3. Move to assembly point: ______________

4. Account for all personnel

5. Report to supervisor

Scaffold Risk Assessment Summary

OVERALL RISK ASSESSMENT:

Based on the identified hazards and existing controls, the overall risk level for this scaffold is:

☐ LOW - Scaffold properly erected, maintained, and used within design parameters

☐ MEDIUM - Moderate hazards present, requires ongoing monitoring

☐ HIGH - Significant hazards identified, requires immediate corrective action

☐ EXTREME - Unsafe conditions present - DO NOT USE

CRITICAL CONTROLS REQUIRED:

1. ______________

2. ______________

3. ______________

4. ______________

5. ______________

MONITORING FREQUENCY:

☐ Continuous monitoring required ☐ Daily inspection ☐ Weekly inspection ☐ Pre-use inspection

☐ Competent person inspection frequency: ______________

WORK STOPPING AUTHORITY:

All personnel have the authority and responsibility to stop work if conditions become unsafe.

Stop work protocol: Notify supervisor immediately, tag scaffold red, secure area.

Certification And Approval

COMPETENT PERSON:

"I have inspected this scaffold and confirm that it has been erected according to design specifications

and is safe for use. All required controls are in place."

Name: ______________ Signature: ______________ Date: ___________

SCAFFOLD SUPERVISOR:

"I have reviewed this risk assessment and confirm that all workers have been trained and understand

the hazards and controls."

Name: ______________ Signature: ______________ Date: ___________

PROJECT MANAGER:

"I approve the use of this scaffold for the intended work activities."

Name: ______________ Signature: ______________ Date: ___________

NEXT INSPECTION DATE: ______________