JSA ID: DEMO-__________ DATE: ______________ TIME: ______________
PROJECT: ______________ LOCATION: ______________ STRUCTURE: ______________
METHOD: ☐ Mechanical ☐ Manual ☐ Implosion STRUCTURE ENGINEER: ______________ CREW SIZE: ______________
| JOB STEP | HAZARDS IDENTIFIED | POTENTIAL CONSEQUENCE | RISK RATING (L x S) | CONTROL MEASURES |
|---|---|---|---|---|
| 1. Engineering Survey | -Unknown structural conditions -Asbestos -Lead paint | -Collapse -Death -Health exposure | 25 (VERY HIGH) | -Structural engineer assessment -Identify load-bearing walls -Check for hazardous materials -Survey for asbestos (AHERA) -Test for lead |
| 2. Utility Isolation | -Live gas -Energized electrical -Water lines -Sewer lines | -Explosion -Electrocution -Fire -Flooding -Contamination | 25 (VERY HIGH) | -Locate all utilities -Cap gas lines -Lockout/tagout electrical -Drain water lines -Notify utility companies |
| 3. Hazardous Material Removal | -Asbestos -Lead dust -Silica dust -PCBs -Mercury | -Lung disease -Poisoning -Silicosis -Cancer | 20 (VERY HIGH) | -Hazardous material abatement first -Licensed abatement contractors -Negative air pressure -HEPA vacuum -Proper disposal manifests |
| 4. Sequential Demolition (Top-Down) | -Uncontrolled collapse -Flying debris -Vibration | -Premature collapse -Struck by -Structural damage | 25 (VERY HIGH) | -Follow engineered sequence -Remove non-load bearing first -Maintain stability -Monitor for movement -Use dust suppression |
| 5. Heavy Equipment Operation | -Equipment instability -Operator visibility -Swing radius | -Tip over -Struck by debris -Crush injuries | 16 (HIGH) | -Grade stable surface -Inspect equipment daily -Exclusion zone 1.5x structure height -Use spotter -Barricade swing area |
| 6. Manual Demolition (Hand Tools ) | -Falls from height -Flying chips -Overexertion -Sharp edges | -Fall from height -Eye injury -Strains -Lacerations | 15 (HIGH) | -Scaffolding or lifts for height -Full body harness -Safety glasses with side shields -Rotate tasks -Heavy leather gloves |
| 7. Debris Handling & Removal | -Dust -Heavy lifting -Sharp objects -Contaminated materials | -Silicosis -Back injury -Puncture wounds -Chemical exposure | 12 (HIGH) | -Water spray for dust control -Mechanical handling equipment -Remove nails from lumber -Separate hazardous waste -Proper disposal containers |
AIR MONITORING: Silica: ______mg/m3 Lead: ______mg/m3 Asbestos: ______f/cc Date: ______________
REQUIRED PPE: ☐ Hard Hat ☐ Safety Glasses ☐ Hearing Protection ☐ N100 Respirator ☐ Tyvek Suit ☐ Gloves
STRUCTURE ENGINEER: ______________ Signature: ______________ Date: ______________
WORKER ACKNOWLEDGMENT: 1. ______________ 2. ______________ 3. ______________