Permit Information

PTW REFERENCE: PTW-______________ CONTRACTOR NAME: ______________

PROJECT NAME: ______________ NO. OF EMPLOYEES INVOLVED: _____

STARTING FROM: ______________ DATE: ______________ TIME: ______________

EXPECTED COMPLETION: ______________ DATE: ______________ TIME: ______________

LIFTING EQUIPMENT TYPE:

☐ Truck Mounted ☐ Crawler Crane ☐ Overhead Crane ☐ Tower Crane ☐ Forklift ☐ Other: ______________

DETAILS OF LOAD:

Weight (approx.): ______________ tons Dimension (max): _______ m x _______ m x _______ m

Quantity of Lifts: ______________ Load Description: ______________

RIGGER LEVEL REQUIRED:

☐ Less than 10 ton ☐ More than 10 to 40 ton ☐ More than 40 ton

DETAILS OF EQUIPMENT:

Equipment ID: ______________ Serial No: ______________

Capacity (SWL): ______________ tons Valid Inspection Date: ______________

Work Details

WORK DESCRIPTION: ______________

______________

LOCATION OF JOB TO BE PERFORMED: ______________

TOOLS/EQUIPMENT TO BE USED: ______________

______________

Hazard Identification

Identify risk associated with Lifting work:

☐ Toppling/Tip Over ☐ Suspended Load ☐ High Wind ☐ Moving Vehicle/Equipment

☐ Falling Objects ☐ Over Load ☐ Tripping/Slipping ☐ Noise

☐ Crushing ☐ Collapse ☐ Near Overhead lines ☐ Traffic

☐ Adverse Weather ☐ Ground Failure ☐ Rigging Failure ☐ Communication Failure

☐ Swing Radius/Crush Zone ☐ Unstable Load ☐ Poor Visibility ☐ Other: ______________

OTHER HAZARDS (Specify): ______________

______________

Attached Documents

The following document must be attached with this permit:YesNoN/A
Method Statement Risk Assessment Lifting Plan Lift Chart / Load Chart Crane Certificate Rigging Gear Certificates Other (specify): ______________☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐

Precaution Measures Checklist

Precaution require to complete the work safelyYesNoN/ARemarks
Is the lifting equipment certified by accredited center? Does certification comply with SEC list? Is the operator certified and hold valid license (KSA) for this activity? Operator Name: ______________ License No: ______________ Expiry: _______ Are all accessories inspected (rigging arrangements)? Checked items:
☐ Wire Rope Sling ☐ Web Sling ☐ Chain Sling ☐ Shackles ☐ Eye Bolt ☐ Other: _____ Is Load Chart checked and applicable? Is the Load within Crane capability at the given radius of operation? Required Capacity: _____ tons @ _____ m radius | Available Capacity: _____ tons Is the rigger certified for this load limit? Name of Rigger: ______________ Rigger Level: _____ Valid Until: _______ Is a Signalman/Banksman appointed? Is wind speed acceptable to proceed the activity? (stop if >32km/h or dusty wind) Is the ground condition suitable and verified? Are outriggers fully extended and properly set on pads? Are outrigger pads/mats of adequate size? Is the crane level (checked with spirit level)? Are there any overhead power lines in the vicinity? If yes, is safe distance maintained as per voltage? Is the swing radius barricaded? Are tag lines provided for load control? Is the load weight verified? Are lifting points on load verified? Is communication system tested and working (radios/hand signals)? Emergency Rescue team and equipment (tower erection) in place?
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
☐
Cert: __ Name: __ Wind: __ Size: __ Level: _ Dist: __ Volt: __ Qty: ___ Weight:_ Channel:

Crane & Rigging Inspection

CRANE INSPECTION ITEMS:STATUSCOMMENTS
Load Moment Indicator (LMI) / Safe Load Indicator (SLI) Anti-two block device Boom angle indicator Hook block / overhaul ball Wire rope condition Sheaves & drums Outriggers / stabilizers Outrigger pads / mats Emergency stop Fire extinguisher in cabWorking ☐ Not Working ☐ Not Accurate ☐ Not Good ☐ Fault ☐ Good ☐ Fault ☐ Good ☐ Fault ☐ Working ☐ Fault Good ☐ Fault ☐ Working ☐ Fault Present ☐ NotCalibrated: ☐ Yes ☐ No Tested: ______________ Reading: ______________ Safety latch: ☐ Yes ☐ No ________ ________ ________ Size: _______ x _______ mm Tested: ______________ Inspected: ______________
RIGGING GEAR INSPECTION:STATUSSWL / COMMENTS
Wire Rope Slings Web / Synthetic Slings Chain Slings Shackles Eye Bolts / Lifting Lugs Spreader Beam / Lifting Beam Lifting Clamps Tag LinesGood ☐ Reject Good ☐ Reject Good ☐ Reject Good ☐ Reject Good ☐ Reject Good ☐ Reject Good ☐ Reject Good ☐ RejectSWL: _______ tons Qty: ___ SWL: _______ tons Qty: ___ SWL: _______ tons Qty: ___ SWL: _______ tons Qty: ___ SWL: _______ tons Qty: ___ SWL: _______ tons SWL: _______ tons Qty: ___ Length: _______ m Qty: ___

INSPECTION CONDUCTED BY: ______________ DATE: ______________ TIME: ______________

(Competent Person / Rigger)

Ground Conditions & Set-Up

GROUND CONDITIONS:

Ground Type: ☐ Concrete ☐ Asphalt ☐ Compacted soil ☐ Gravel ☐ Clay ☐ Other: ______________

Ground Bearing Capacity: ______________ kPa / tons/m² Verified by: ______________

Ground Condition: ☐ Dry ☐ Wet ☐ Frozen ☐ Unstable ☐ Other: ______________

OUTRIGGER SET-UP:

Outrigger Configuration: ☐ Fully Extended ☐ Partially Extended (refer to load chart)

Outrigger Pad Size: ______________ x ______________ mm

Outrigger Cribbing/Mats Used: ☐ Yes ☐ No Type: ☐ Timber ☐ Steel ☐ Composite

Cribbing Size: ______________ x ______________ mm Thickness: ______________ mm

SITE HAZARDS:

Overhead Power Lines: ☐ Yes ☐ No Voltage: ______________ kV Distance: ______________ m

Underground Services: ☐ Yes ☐ No Marked/Protected: ☐ Yes ☐ No

Nearby Structures/Obstructions: ☐ Yes ☐ No Description: ______________

Other Cranes/Equipment in Area: ☐ Yes ☐ No SIMOPS Coordination: ☐ Yes ☐ No

SET-UP VERIFIED BY: ______________ DATE: ______________ TIME: ______________

Critical Lift / Man Basket (If Applicable)

CRITICAL LIFT (>40 tons or special lifts):

☐ Critical Lift Plan approved by Engineer

☐ Third party inspection completed

☐ Additional safety factors applied (1.5x)

☐ All personnel briefed on critical lift procedures

PERSONNEL LIFT (MAN BASKET):

☐ Man basket certified and load tested within 12 months

☐ Man basket SWL: _______ persons or _______ kg

☐ Crane certified for personnel lifting

☐ Anti-two block device working

☐ Positive means of attachment on hook (safety pin/bolt)

☐ Personnel wearing full body harness attached to independent line

☐ Rescue plan for suspended personnel in place

APPROVED BY: ______________ DATE: ______________

Inspection Checklist (Issuer & Receiver)

The following areas / items have been inspected by issuer and receiver:

ITEMSTATUSCOMMENTS
Ground Condition Danger / Warning Signs Signalman / Banksman Safety Barriers / Barricades Tag Line(s) Rigger(s) Outrigger(s) - Extended Outrigger Pad(s) Lighting (if night work) Spreader Beam (if used) Man/Material Basket (if used) Communication Radios Wind Speed MonitorAccept ☐ Not In Place ☐ Not Assigned ☐ Not In Place ☐ Not Available ☐ Not Assigned ☐ Not Yes ☐ No ☐ In Place ☐ Not Adequate ☐ Not Certified ☐ Not Certified ☐ Not Working ☐ Not Working ☐ Not________ ________ Name: ______________ Swing radius barricaded: ☐ Yes ☐ No Qty: _____ Condition: ☐ Good ☐ Poor Names: ______________ All outriggers properly extended? Size adequate? ☐ Yes ☐ No Lux level: _____ SWL: _____ tons Cert #: _________ SWL: _____ tons Cert Date: _________ Channel: _____ Backup available: ☐ Yes ☐ No Current reading: _____ km/h

OTHER ITEMS (Specify):

______________

INSPECTED BY (Issuer): ______________ DATE: ______________ TIME: ______________

INSPECTED BY (Receiver): ______________ DATE: ______________ TIME: ______________

Personal Protective Equipment (Ppe)

PPE Required for the activity:

MANDATORY PPE:

☐ Helmet / Hard hat ☐ Safety Shoes / Steel-toed boots ☐ Reflective Vest

☐ Safety Goggles / Glasses ☐ Mechanical Gloves ☐ Safety Ear Plugs / Muffs

☐ High Visibility Clothing ☐ Safety Clothes / Coveralls

ADDITIONAL PPE (as required):

☐ Safety Harness / Fall Arrest (for work at height) ☐ Face Shield

☐ Dust Mask / Respirator ☐ Sun Protection ☐ Other: ______________

PPE VERIFIED BY: ______________ DATE: ______________ TIME: ______________

Pre-Lift Meeting / Toolbox Talk

TOPICS COVERED:

☐ Lift details & sequence ☐ Roles & responsibilities ☐ Load weight & characteristics

☐ Crane capacity & limitations ☐ Rigging configuration ☐ Communication methods & signals

☐ Hazard identification ☐ Control measures ☐ Exclusion zone / barricades

☐ Emergency procedures ☐ Stop work authority ☐ Weather constraints

ATTENDEES:

NAMEROLECOMPANYSIGNATURE
________ ________ ________ ________ ________ ________________ ________ ________ ________ ________ ________________ ________ ________ ________ ________ ________________ ________ ________ ________ ________ ________

MEETING CONDUCTED BY: ______________ DATE: ______________ TIME: ______________

Lift Execution Record

TEST LIFT / TRIAL LIFT:

Test lift performed with load just off ground? ☐ Yes ☐ No Time: ______________

Brakes tested? ☐ Yes ☐ No All systems functioning? ☐ Yes ☐ No

LIFT COMMENCEMENT: Time: ______________ LIFT COMPLETION: Time: ______________

LIFT LOG:

TIMEOBSERVATIONINITIALS
______ ______ ______________ ________ _______________ _______ _______

ANY ISSUES DURING LIFT? ☐ No ☐ Yes (describe): ______________

Authorization Sign-Off

PERMIT RECEIVER / LIFT SUPERVISOR (Confirms all preparations complete):

I confirm that this lifting operation has been properly planned, all hazards assessed, all equipment

inspected, and the team briefed. Safe to proceed.

Name: ______________ Signature: ______________ Date: ___________

CRANE OPERATOR (Confirms crane safe and load within capacity):

I confirm that the crane is in safe working condition, the load is within capacity at the working radius.

Name: ______________ Signature: ______________ Date: ___________

RIGGER IN-CHARGE (Confirms rigging correct and load secure):

I confirm that all rigging is correctly configured, within SWL, and the load is properly attached.

Name: ______________ Signature: ______________ Date: ___________

SIGNALMAN / BANKSMAN (Confirms communication and signals):

I confirm that communication systems are working and hand signals are understood by all.

Name: ______________ Signature: ______________ Date: ___________

SAFETY OFFICER (Verifies controls in place):

Name: ______________ Signature: ______________ Date: ___________

PERMIT ISSUER (Authorizes work to proceed):

I have reviewed all aspects and authorize the lifting operation to proceed.

Name: ______________ Signature: ______________ Date: ___________

Lift Completion / Handover

LIFT COMPLETED / SUSPENDED:

Date: ______________ Time: ______________ ☐ Completed ☐ Suspended ☐ Aborted

CRANE SECURED:

☐ Boom lowered / secured ☐ Engine off / key removed ☐ Outriggers retracted

☐ Crane parked in designated area

RIGGING EQUIPMENT:

☐ All rigging removed and stored ☐ Rigging inspected for damage

☐ Damaged rigging tagged and removed from service

SITE RESTORATION:

☐ Area cleared ☐ Barricades removed ☐ Area returned to Operations

LIFT SUPERVISOR SIGN-OFF: ______________ Date: ______________

AREA AUTHORITY SIGN-OFF: ______________ Date: ______________