Free Lifting Operation Permit (Enhanced) template for construction you can edit online and download as PDF. Covers permit information, work details, hazard identification.
PTW REFERENCE: PTW-______________ CONTRACTOR NAME: ______________
PROJECT NAME: ______________ NO. OF EMPLOYEES INVOLVED: _____
STARTING FROM: ______________ DATE: ______________ TIME: ______________
EXPECTED COMPLETION: ______________ DATE: ______________ TIME: ______________
LIFTING EQUIPMENT TYPE:
☐ Truck Mounted ☐ Crawler Crane ☐ Overhead Crane ☐ Tower Crane ☐ Forklift ☐ Other: ______________
DETAILS OF LOAD:
Weight (approx.): ______________ tons Dimension (max): _______ m x _______ m x _______ m
Quantity of Lifts: ______________ Load Description: ______________
RIGGER LEVEL REQUIRED:
☐ Less than 10 ton ☐ More than 10 to 40 ton ☐ More than 40 ton
DETAILS OF EQUIPMENT:
Equipment ID: ______________ Serial No: ______________
Capacity (SWL): ______________ tons Valid Inspection Date: ______________
WORK DESCRIPTION: ______________
______________
LOCATION OF JOB TO BE PERFORMED: ______________
TOOLS/EQUIPMENT TO BE USED: ______________
______________
Identify risk associated with Lifting work:
☐ Toppling/Tip Over ☐ Suspended Load ☐ High Wind ☐ Moving Vehicle/Equipment
☐ Falling Objects ☐ Over Load ☐ Tripping/Slipping ☐ Noise
☐ Crushing ☐ Collapse ☐ Near Overhead lines ☐ Traffic
☐ Adverse Weather ☐ Ground Failure ☐ Rigging Failure ☐ Communication Failure
☐ Swing Radius/Crush Zone ☐ Unstable Load ☐ Poor Visibility ☐ Other: ______________
OTHER HAZARDS (Specify): ______________
______________
| The following document must be attached with this permit: | Yes | No | N/A |
|---|---|---|---|
| Method Statement Risk Assessment Lifting Plan Lift Chart / Load Chart Crane Certificate Rigging Gear Certificates Other (specify): ______________ | ☐ ☐ ☐ ☐ ☐ ☐ ☐ | ☐ ☐ ☐ ☐ ☐ ☐ ☐ | ☐ ☐ ☐ ☐ ☐ ☐ ☐ |
| Precaution require to complete the work safely | Yes | No | N/A | Remarks |
|---|---|---|---|---|
| Is the lifting equipment certified by accredited center? Does certification comply with SEC list? Is the operator certified and hold valid license (KSA) for this activity? Operator Name: ______________ License No: ______________ Expiry: _______ Are all accessories inspected (rigging arrangements)? Checked items: ☐ Wire Rope Sling ☐ Web Sling ☐ Chain Sling ☐ Shackles ☐ Eye Bolt ☐ Other: _____ Is Load Chart checked and applicable? Is the Load within Crane capability at the given radius of operation? Required Capacity: _____ tons @ _____ m radius | Available Capacity: _____ tons Is the rigger certified for this load limit? Name of Rigger: ______________ Rigger Level: _____ Valid Until: _______ Is a Signalman/Banksman appointed? Is wind speed acceptable to proceed the activity? (stop if >32km/h or dusty wind) Is the ground condition suitable and verified? Are outriggers fully extended and properly set on pads? Are outrigger pads/mats of adequate size? Is the crane level (checked with spirit level)? Are there any overhead power lines in the vicinity? If yes, is safe distance maintained as per voltage? Is the swing radius barricaded? Are tag lines provided for load control? Is the load weight verified? Are lifting points on load verified? Is communication system tested and working (radios/hand signals)? Emergency Rescue team and equipment (tower erection) in place? | ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ | ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ | ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ ☐ | Cert: __ Name: __ Wind: __ Size: __ Level: _ Dist: __ Volt: __ Qty: ___ Weight:_ Channel: |
| CRANE INSPECTION ITEMS: | STATUS | COMMENTS |
|---|---|---|
| Load Moment Indicator (LMI) / Safe Load Indicator (SLI) Anti-two block device Boom angle indicator Hook block / overhaul ball Wire rope condition Sheaves & drums Outriggers / stabilizers Outrigger pads / mats Emergency stop Fire extinguisher in cab | Working ☐ Not Working ☐ Not Accurate ☐ Not Good ☐ Fault ☐ Good ☐ Fault ☐ Good ☐ Fault ☐ Working ☐ Fault Good ☐ Fault ☐ Working ☐ Fault Present ☐ Not | Calibrated: ☐ Yes ☐ No Tested: ______________ Reading: ______________ Safety latch: ☐ Yes ☐ No ________ ________ ________ Size: _______ x _______ mm Tested: ______________ Inspected: ______________ |
| RIGGING GEAR INSPECTION: | STATUS | SWL / COMMENTS |
| Wire Rope Slings Web / Synthetic Slings Chain Slings Shackles Eye Bolts / Lifting Lugs Spreader Beam / Lifting Beam Lifting Clamps Tag Lines | Good ☐ Reject Good ☐ Reject Good ☐ Reject Good ☐ Reject Good ☐ Reject Good ☐ Reject Good ☐ Reject Good ☐ Reject | SWL: _______ tons Qty: ___ SWL: _______ tons Qty: ___ SWL: _______ tons Qty: ___ SWL: _______ tons Qty: ___ SWL: _______ tons Qty: ___ SWL: _______ tons SWL: _______ tons Qty: ___ Length: _______ m Qty: ___ |
INSPECTION CONDUCTED BY: ______________ DATE: ______________ TIME: ______________
(Competent Person / Rigger)
GROUND CONDITIONS:
Ground Type: ☐ Concrete ☐ Asphalt ☐ Compacted soil ☐ Gravel ☐ Clay ☐ Other: ______________
Ground Bearing Capacity: ______________ kPa / tons/m² Verified by: ______________
Ground Condition: ☐ Dry ☐ Wet ☐ Frozen ☐ Unstable ☐ Other: ______________
OUTRIGGER SET-UP:
Outrigger Configuration: ☐ Fully Extended ☐ Partially Extended (refer to load chart)
Outrigger Pad Size: ______________ x ______________ mm
Outrigger Cribbing/Mats Used: ☐ Yes ☐ No Type: ☐ Timber ☐ Steel ☐ Composite
Cribbing Size: ______________ x ______________ mm Thickness: ______________ mm
SITE HAZARDS:
Overhead Power Lines: ☐ Yes ☐ No Voltage: ______________ kV Distance: ______________ m
Underground Services: ☐ Yes ☐ No Marked/Protected: ☐ Yes ☐ No
Nearby Structures/Obstructions: ☐ Yes ☐ No Description: ______________
Other Cranes/Equipment in Area: ☐ Yes ☐ No SIMOPS Coordination: ☐ Yes ☐ No
SET-UP VERIFIED BY: ______________ DATE: ______________ TIME: ______________
CRITICAL LIFT (>40 tons or special lifts):
☐ Critical Lift Plan approved by Engineer
☐ Third party inspection completed
☐ Additional safety factors applied (1.5x)
☐ All personnel briefed on critical lift procedures
PERSONNEL LIFT (MAN BASKET):
☐ Man basket certified and load tested within 12 months
☐ Man basket SWL: _______ persons or _______ kg
☐ Crane certified for personnel lifting
☐ Anti-two block device working
☐ Positive means of attachment on hook (safety pin/bolt)
☐ Personnel wearing full body harness attached to independent line
☐ Rescue plan for suspended personnel in place
APPROVED BY: ______________ DATE: ______________
The following areas / items have been inspected by issuer and receiver:
| ITEM | STATUS | COMMENTS |
|---|---|---|
| Ground Condition Danger / Warning Signs Signalman / Banksman Safety Barriers / Barricades Tag Line(s) Rigger(s) Outrigger(s) - Extended Outrigger Pad(s) Lighting (if night work) Spreader Beam (if used) Man/Material Basket (if used) Communication Radios Wind Speed Monitor | Accept ☐ Not In Place ☐ Not Assigned ☐ Not In Place ☐ Not Available ☐ Not Assigned ☐ Not Yes ☐ No ☐ In Place ☐ Not Adequate ☐ Not Certified ☐ Not Certified ☐ Not Working ☐ Not Working ☐ Not | ________ ________ Name: ______________ Swing radius barricaded: ☐ Yes ☐ No Qty: _____ Condition: ☐ Good ☐ Poor Names: ______________ All outriggers properly extended? Size adequate? ☐ Yes ☐ No Lux level: _____ SWL: _____ tons Cert #: _________ SWL: _____ tons Cert Date: _________ Channel: _____ Backup available: ☐ Yes ☐ No Current reading: _____ km/h |
OTHER ITEMS (Specify):
______________
INSPECTED BY (Issuer): ______________ DATE: ______________ TIME: ______________
INSPECTED BY (Receiver): ______________ DATE: ______________ TIME: ______________
PPE Required for the activity:
MANDATORY PPE:
☐ Helmet / Hard hat ☐ Safety Shoes / Steel-toed boots ☐ Reflective Vest
☐ Safety Goggles / Glasses ☐ Mechanical Gloves ☐ Safety Ear Plugs / Muffs
☐ High Visibility Clothing ☐ Safety Clothes / Coveralls
ADDITIONAL PPE (as required):
☐ Safety Harness / Fall Arrest (for work at height) ☐ Face Shield
☐ Dust Mask / Respirator ☐ Sun Protection ☐ Other: ______________
PPE VERIFIED BY: ______________ DATE: ______________ TIME: ______________
TOPICS COVERED:
☐ Lift details & sequence ☐ Roles & responsibilities ☐ Load weight & characteristics
☐ Crane capacity & limitations ☐ Rigging configuration ☐ Communication methods & signals
☐ Hazard identification ☐ Control measures ☐ Exclusion zone / barricades
☐ Emergency procedures ☐ Stop work authority ☐ Weather constraints
ATTENDEES:
| NAME | ROLE | COMPANY | SIGNATURE | ||
|---|---|---|---|---|---|
| ________ ________ ________ ________ ________ ________ | ________ ________ ________ ________ ________ ________ | ________ ________ ________ ________ ________ ________ | ________ ________ ________ ________ ________ ________ |
MEETING CONDUCTED BY: ______________ DATE: ______________ TIME: ______________
TEST LIFT / TRIAL LIFT:
Test lift performed with load just off ground? ☐ Yes ☐ No Time: ______________
Brakes tested? ☐ Yes ☐ No All systems functioning? ☐ Yes ☐ No
LIFT COMMENCEMENT: Time: ______________ LIFT COMPLETION: Time: ______________
LIFT LOG:
| TIME | OBSERVATION | INITIALS | ||
|---|---|---|---|---|
| ______ ______ ______ | ________ ________ ________ | _______ _______ _______ |
ANY ISSUES DURING LIFT? ☐ No ☐ Yes (describe): ______________
PERMIT RECEIVER / LIFT SUPERVISOR (Confirms all preparations complete):
I confirm that this lifting operation has been properly planned, all hazards assessed, all equipment
inspected, and the team briefed. Safe to proceed.
Name: ______________ Signature: ______________ Date: ___________
CRANE OPERATOR (Confirms crane safe and load within capacity):
I confirm that the crane is in safe working condition, the load is within capacity at the working radius.
Name: ______________ Signature: ______________ Date: ___________
RIGGER IN-CHARGE (Confirms rigging correct and load secure):
I confirm that all rigging is correctly configured, within SWL, and the load is properly attached.
Name: ______________ Signature: ______________ Date: ___________
SIGNALMAN / BANKSMAN (Confirms communication and signals):
I confirm that communication systems are working and hand signals are understood by all.
Name: ______________ Signature: ______________ Date: ___________
SAFETY OFFICER (Verifies controls in place):
Name: ______________ Signature: ______________ Date: ___________
PERMIT ISSUER (Authorizes work to proceed):
I have reviewed all aspects and authorize the lifting operation to proceed.
Name: ______________ Signature: ______________ Date: ___________
LIFT COMPLETED / SUSPENDED:
Date: ______________ Time: ______________ ☐ Completed ☐ Suspended ☐ Aborted
CRANE SECURED:
☐ Boom lowered / secured ☐ Engine off / key removed ☐ Outriggers retracted
☐ Crane parked in designated area
RIGGING EQUIPMENT:
☐ All rigging removed and stored ☐ Rigging inspected for damage
☐ Damaged rigging tagged and removed from service
SITE RESTORATION:
☐ Area cleared ☐ Barricades removed ☐ Area returned to Operations
LIFT SUPERVISOR SIGN-OFF: ______________ Date: ______________
AREA AUTHORITY SIGN-OFF: ______________ Date: ______________
THIS PERMIT IS VALID ONLY FOR THE DATE AND TIME SPECIFIED - ONE SHIFT ONLY