Free Enclosed Spaces Risk Assessment template for maritime you can edit online and download as PDF. Covers assessment information, atmospheric hazard assessment, physical & environmental hazards.
ASSESSMENT ID: ESRA-__________ VESSEL: ______________ LOCATION: ______________
ASSESSMENT DATE: ______________ ENTRY PURPOSE: ☐ Inspection ☐ Maintenance
SPACE TYPE: ☐ Emergency ☐ Cleaning ☐ Repair
☐ Tank ☐ Hold ☐ Void ☐ Machinery ☐ Pipe Duct ☐ Other: __________
LAST ENTRY DATE: ______________ ANTICIPATED DURATION: ______ hours TEMPERATURE: ______°C
| ATMOSPHERIC HAZARD | PRE-ENTRY READING | CONTINUOUS MONITORING | SAFE LEVEL | ACTUAL LEVEL | RISK STATUS |
|---|---|---|---|---|---|
| Oxygen | 20.9% | 20.8% | 19.5-23.5% | 20.8% | SAFE |
| LEL (Lower Explosive) | 0% LEL | 0% LEL | <10% LEL | 0% LEL | SAFE |
| H2S (Hydrogen Sulfide) | 0 ppm | 0 ppm | <10 ppm | 0 ppm | SAFE |
| CO (Carbon Monoxide) | 0 ppm | 2 ppm | <35 ppm | 2 ppm | SAFE |
| VOC (Volatile Organic) | 0 ppm | 0 ppm | <100 ppm | 0 ppm | SAFE |
| PHYSICAL HAZARD | PRESENT (Y/N) | RISK LEVEL | CONTROL MEASURES | EMERGENCY EQUIPMENT | RESIDUAL RISK |
|---|---|---|---|---|---|
| Engulfment Hazard | Yes | HIGH | Lockout/Tagout Procedures | Rescue Harness & Tripod | MEDIUM |
| Electrical Hazards | Yes | MEDIUM | Isolation & Grounding | Non-sparking Tools | LOW |
| Temperature Extremes | No | LOW | Ventilation | Cooling Vest | LOW |
| Physical Obstructions | Yes | MEDIUM | Safe Access & Lighting | Stretcher | MEDIUM |
| TEAM MEMBER | ROLE | TRAINING STATUS | MEDICAL FITNESS | EQUIPMENT CHECKED | COMMUNICATION METHOD |
|---|---|---|---|---|---|
| _____________ | ☐ Entry | Current | Fit | Complete | Radio / Sounder |
| _____________ | ☐ Attendant | Current | Fit | Complete | Visual / Phone |
| _____________ | ☐ Supervisor | Current | Fit | Complete | Radio / Phone |
| _____________ | ☐ Standby | Current | Fit | Complete | Radio / Alarm |
| EMERGENCY SCENARIO | RESPONSE TEAM | EQUIPMENT AVAILABLE | RESPONSE TIME | MEDICAL SUPPORT | DRILL LAST CONDUCTED |
|---|---|---|---|---|---|
| Atmospheric Hazard | Standby Team | BA Sets | <2 mins | Onboard Medical | Last Month |
| Entrapment/ Injury | Trained Crew | Rescue Equipment | <5 mins | First Aid Team | Quarterly |
| Medical Emergency | Trained Personnel | Medical Kit | <3 mins | Medical Center | Semi-Annual |
ENTRY PERMIT AUTHORIZATION:
• Space adequately ventilated and gas-free verified
• All energy sources isolated and locked out
• Emergency arrangements confirmed and operational
• Communication systems tested and functional
• Personnel trained and equipped appropriately
• Standby rescue team in position
ENTRY SUPERVISOR: ______________ TIME IN: ______________
ENTRY ATTENDANT: ______________ TIME OUT: ______________
MASTER'S APPROVAL: ______________ DATE: ______________
PERMIT VALID FOR: 8 HOURS MAXIMUM (EXTENDABLE ONLY WITH RE-ASSESSMENT)
╰─────────────────────────────────────────────────────────────────────────────────────────────────────────────────╯